O | UNIT OR AREA | DURATION | START | FINISH |
---|---|---|---|---|
2 | 42 Floor Hall Lateral work (Zones: 1, 3, and 6) | 38 days | Thu 3/31/22 | Mon 5/23/22 |
3 | 42A Lateral Work (Zones: 1, 2 and 3) | 30 days | Thu 3/31/22 | Wed 5/11/22 |
4 | 41B Lateral Work (Zone: 3) | 10 days | Mon 4/11/22 | Fri 4/22/22 |
5 | 41C Lateral Work (Zone: 1) | 10 days | Mon 4/11/22 | Fri 4/22/22 |
6 | 40A Lateral Work (Zone: 3) | 30 days | Mon 4/4/22 | Fri 5/13/22 |
7 | 42D Lateral Work (Zones: 3 and 5) | 30 days | Thu 4/14/22 | Wed 5/25/22 |
8 | 41K Lateral Work (Zone 5) | 16 days | Wed 4/13/22 | Wed 5/4/22 |
9 | 41L Lateral Work (Zone 5) | 10 days | Thu 4/21/22 | Wed 5/4/22 |
10 | 41M Lateral Work (Zone 3) | 10 days | Thu 4/21/22 | Wed 5/4/22 |
11 | 41A/N Lateral Work (Zone 3) | 36 days | Fri 4/1/22 | Fri 5/20/22 |
12 | 40N Lateral Work (Zone 3) | 40 days | Mon 4/4/22 | Fri 5/27/22 |
13 | 42B Lateral Work (Zone 1 and 2) | 39 days | Tue 4/5/22 | Fri 5/27/22 |
14 | 41G Lateral Work (Zone 2) | 41 days | Fri 4/1/22 | Fri 5/27/22 |
15 | 41F Lateral Work (Zone 2) | 10 days | Wed 5/4/22 | Tue 5/17/22 |
16 | 42C Lateral Work (Zones: 2 and 5) | 36 days | Fri 4/8/22 | Fri 5/27/22 |
17 | 41H Lateral Work (Zone 2) | 40 days | Mon 4/4/22 | Fri 5/27/22 |
18 | 41I Lateral Work (Zone 2) | 10 days? | Mon 5/16/22 | Fri 5/27/22 |
19 | 41J Lateral Work (Zone 5) | 10 days | Mon 5/16/22 | Fri 5/27/22 |