O | Unit Name | Task Name | Duration | Start | Finish | |
---|---|---|---|---|---|---|
3 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | 34 days | Mon 8/3/20 | Fri 9/18/20 | ||
4 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | Demoltion & Abatement | 2 days | Mon 8/3/20 | Tue 8/4/20 | |
5 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | Plumbing Replacement & Inspections | 5 days | Wed 8/5/20 | Tue 8/11/20 | |
6 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | Drywall Repair & Inspections | 9 days | Wed 8/12/20 | Mon 8/24/20 | |
7 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | Texture/Paint | 6 days | Tue 8/25/20 | Tue 9/1/20 | |
8 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | Tile, Carpentry & Reconstruction | 10 days | Wed 9/2/20 | Wed 9/16/20 | |
9 | PH 42A/42B Final Pass DWV & Domestic & HVAC Replacement | Substantial Completion & Punchlist | 2 days | Thu 9/17/20 | Fri 9/18/20 | |
10 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | 34 days | Mon 8/3/20 | Fri 9/18/20 | ||
11 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 8/3/20 | Tue 8/4/20 | |
12 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 5 days | Tue 8/4/20 | Mon 8/10/20 | |
13 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 8/11/20 | Thu 8/20/20 | |
14 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 6 days | Fri 8/21/20 | Fri 8/28/20 | |
15 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 12 days | Mon 8/31/20 | Wed 9/16/20 | |
16 | 41C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Thu 9/17/20 | Fri 9/18/20 | |
17 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | 34 days | Mon 8/10/20 | Fri 9/25/20 | ||
18 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 8/10/20 | Tue 8/11/20 | |
19 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 8/11/20 | Thu 8/13/20 | |
20 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 9 days | Fri 8/14/20 | Wed 8/26/20 | |
21 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 6 days | Thu 8/27/20 | Thu 9/3/20 | |
22 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 13 days | Fri 9/4/20 | Wed 9/23/20 | |
23 | 40C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Thu 9/24/20 | Fri 9/25/20 | |
24 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | 34 days | Tue 8/11/20 | Mon 9/28/20 | ||
25 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 8/11/20 | Wed 8/12/20 | |
26 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 8/12/20 | Fri 8/14/20 | |
27 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 8/17/20 | Wed 8/26/20 | |
28 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 5 days | Thu 8/27/20 | Wed 9/2/20 | |
29 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 9/3/20 | Thu 9/24/20 | |
30 | 39C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Fri 9/25/20 | Mon 9/28/20 | |
31 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | 34 days | Wed 8/12/20 | Tue 9/29/20 | ||
32 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 8/12/20 | Thu 8/13/20 | |
33 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 8/13/20 | Mon 8/17/20 | |
34 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 8/18/20 | Thu 8/27/20 | |
35 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 5 days | Fri 8/28/20 | Thu 9/3/20 | |
36 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Fri 9/4/20 | Fri 9/25/20 | |
37 | 38C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Mon 9/28/20 | Tue 9/29/20 | |
38 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | 34 days | Thu 8/13/20 | Wed 9/30/20 | ||
39 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 8/13/20 | Fri 8/14/20 | |
40 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 8/14/20 | Tue 8/18/20 | |
41 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 8/19/20 | Fri 8/28/20 | |
42 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 5 days | Mon 8/31/20 | Fri 9/4/20 | |
43 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 9/8/20 | Mon 9/28/20 | |
44 | 37C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Tue 9/29/20 | Wed 9/30/20 | |
45 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | 34 days | Fri 8/14/20 | Thu 10/1/20 | ||
46 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 8/14/20 | Mon 8/17/20 | |
47 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 8/17/20 | Wed 8/19/20 | |
48 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 8/20/20 | Mon 8/31/20 | |
49 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 5 days | Tue 9/1/20 | Tue 9/8/20 | |
50 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 9/9/20 | Tue 9/29/20 | |
51 | 36C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Wed 9/30/20 | Thu 10/1/20 | |
52 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | 34 days | Mon 8/17/20 | Fri 10/2/20 | ||
53 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 8/17/20 | Tue 8/18/20 | |
54 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 8/18/20 | Thu 8/20/20 | |
55 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 8/21/20 | Tue 9/1/20 | |
56 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | Texture/Paint | 5 days | Wed 9/2/20 | Wed 9/9/20 | |
57 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 9/10/20 | Wed 9/30/20 | |
58 | 35C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Thu 10/1/20 | Fri 10/2/20 | |
59 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | 34 days | Tue 8/18/20 | Mon 10/5/20 | ||
60 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 8/18/20 | Wed 8/19/20 | |
61 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 8/19/20 | Fri 8/21/20 | |
62 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 8/24/20 | Wed 9/2/20 | |
63 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Thu 9/3/20 | Thu 9/10/20 | |
64 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Fri 9/11/20 | Thu 10/1/20 | |
65 | 34D Bathroom & 34D/E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Fri 10/2/20 | Mon 10/5/20 | |
66 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | 34 days | Wed 8/19/20 | Tue 10/6/20 | ||
67 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 8/19/20 | Thu 8/20/20 | |
68 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 8/20/20 | Mon 8/24/20 | |
69 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 8/25/20 | Thu 9/3/20 | |
70 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Fri 9/4/20 | Fri 9/11/20 | |
71 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 9/14/20 | Fri 10/2/20 | |
72 | 33D Bathroom & 33D/33E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Mon 10/5/20 | Tue 10/6/20 | |
73 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | 34 days | Thu 8/20/20 | Wed 10/7/20 | ||
74 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 8/20/20 | Fri 8/21/20 | |
75 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 8/21/20 | Tue 8/25/20 | |
76 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 8/26/20 | Fri 9/4/20 | |
77 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 9/8/20 | Mon 9/14/20 | |
78 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 9/15/20 | Mon 10/5/20 | |
79 | 32D Bathroom & 32D/32E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Tue 10/6/20 | Wed 10/7/20 | |
80 | CDE Work Pause for Recovery Schedule | 15 days | Wed 9/2/20 | Wed 9/23/20 | ||
81 | Riser Valve Installation [SHOULDER] | 13 days | Wed 9/9/20 | Fri 9/25/20 | ||
82 | Riser Valve Installation [SHOULDER] | Demo / Abatement | 3 days | Wed 9/9/20 | Fri 9/11/20 | |
83 | Riser Valve Installation [SHOULDER] | Plumbing Valve Repalcmet | 10 days | Mon 9/14/20 | Fri 9/25/20 | |
84 | Riser Valve Installation [SHOULDER] | Temp Access Coverings | 0 days | Fri 9/25/20 | Fri 9/25/20 | |
85 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | 44 days | Wed 9/23/20 | Mon 11/23/20 | ||
86 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 9/23/20 | Thu 9/24/20 | |
87 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 9/24/20 | Mon 9/28/20 | |
88 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 9/29/20 | Thu 10/8/20 | |
89 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Fri 10/9/20 | Thu 10/15/20 | |
90 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Fri 10/16/20 | Thu 11/5/20 | |
91 | 31D Bathroom & 31D/31E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 12 days | Fri 11/6/20 | Mon 11/23/20 | |
92 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | 44 days | Thu 9/24/20 | Tue 11/24/20 | ||
93 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 9/24/20 | Fri 9/25/20 | |
94 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 9/25/20 | Tue 9/29/20 | |
95 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 9/30/20 | Fri 10/9/20 | |
96 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Mon 10/12/20 | Fri 10/16/20 | |
97 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 10/19/20 | Fri 11/6/20 | |
98 | 30D Bathroom & 30D/30E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 12 days | Mon 11/9/20 | Tue 11/24/20 | |
99 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | 44 days | Fri 9/25/20 | Wed 11/25/20 | ||
100 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 9/25/20 | Mon 9/28/20 | |
101 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 9/28/20 | Wed 9/30/20 | |
102 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 10/1/20 | Mon 10/12/20 | |
103 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 10/13/20 | Mon 10/19/20 | |
104 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 10/20/20 | Mon 11/9/20 | |
105 | 29D Bathroom & 29D/29E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 12 days | Tue 11/10/20 | Wed 11/25/20 | |
106 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | 44 days | Mon 9/28/20 | Mon 11/30/20 | ||
107 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 9/28/20 | Tue 9/29/20 | |
108 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 9/29/20 | Thu 10/1/20 | |
109 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 10/2/20 | Tue 10/13/20 | |
110 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Wed 10/14/20 | Tue 10/20/20 | |
111 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 10/21/20 | Tue 11/10/20 | |
112 | 28D Bathroom & 28D/28E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 12 days | Wed 11/11/20 | Mon 11/30/20 | |
113 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | 44 days | Tue 9/29/20 | Tue 12/1/20 | ||
114 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 9/29/20 | Wed 9/30/20 | |
115 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 9/30/20 | Fri 10/2/20 | |
116 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 10/5/20 | Wed 10/14/20 | |
117 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Thu 10/15/20 | Wed 10/21/20 | |
118 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 10/22/20 | Wed 11/11/20 | |
119 | 27D Bathroom & 27D/27E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 12 days | Thu 11/12/20 | Tue 12/1/20 | |
120 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | 35 days | Wed 9/30/20 | Tue 11/17/20 | ||
121 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 9/30/20 | Thu 10/1/20 | |
122 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 10/1/20 | Mon 10/5/20 | |
123 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 10/6/20 | Thu 10/15/20 | |
124 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Fri 10/16/20 | Thu 10/22/20 | |
125 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Fri 10/23/20 | Thu 11/12/20 | |
126 | 26D Bathroom & 26D/26E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Fri 11/13/20 | Tue 11/17/20 | |
127 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | 35 days | Thu 10/1/20 | Wed 11/18/20 | ||
128 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 10/1/20 | Fri 10/2/20 | |
129 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 10/2/20 | Tue 10/6/20 | |
130 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 10/7/20 | Fri 10/16/20 | |
131 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Mon 10/19/20 | Fri 10/23/20 | |
132 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 10/26/20 | Fri 11/13/20 | |
133 | 25D Bathroom & 25D/25E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Mon 11/16/20 | Wed 11/18/20 | |
134 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | 35 days | Fri 10/2/20 | Thu 11/19/20 | ||
135 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 10/2/20 | Mon 10/5/20 | |
136 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 10/5/20 | Wed 10/7/20 | |
137 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 10/8/20 | Mon 10/19/20 | |
138 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 10/20/20 | Mon 10/26/20 | |
139 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 10/27/20 | Mon 11/16/20 | |
140 | 24D Bathroom & 24D/24E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Tue 11/17/20 | Thu 11/19/20 | |
141 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | 35 days | Mon 10/5/20 | Fri 11/20/20 | ||
142 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 10/5/20 | Tue 10/6/20 | |
143 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 10/6/20 | Thu 10/8/20 | |
144 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 10/9/20 | Tue 10/20/20 | |
145 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Wed 10/21/20 | Tue 10/27/20 | |
146 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 10/28/20 | Tue 11/17/20 | |
147 | 23D Bathroom & 23D/23E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Wed 11/18/20 | Fri 11/20/20 | |
148 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | 34 days | Mon 10/12/20 | Mon 11/30/20 | ||
149 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 10/12/20 | Tue 10/13/20 | |
150 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 10/13/20 | Thu 10/15/20 | |
151 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 10/16/20 | Tue 10/27/20 | |
152 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Wed 10/28/20 | Tue 11/3/20 | |
153 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 11/4/20 | Tue 11/24/20 | |
154 | 22D Bathroom & 22D/22E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 2 days | Wed 11/25/20 | Mon 11/30/20 | |
155 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | 35 days | Tue 10/13/20 | Wed 12/2/20 | ||
156 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 10/13/20 | Wed 10/14/20 | |
157 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 10/14/20 | Fri 10/16/20 | |
158 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 10/19/20 | Wed 10/28/20 | |
159 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Thu 10/29/20 | Wed 11/4/20 | |
160 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 11/5/20 | Wed 11/25/20 | |
161 | 21D Bathroom & 21D/21E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Mon 11/30/20 | Wed 12/2/20 | |
162 | 20D Bathroom & 20D/20E Kitchen | 35 days | Wed 10/14/20 | Thu 12/3/20 | ||
163 | 20D Bathroom & 20D/20E Kitchen | Demoltion & Abatement | 2 days | Wed 10/14/20 | Thu 10/15/20 | |
164 | 20D Bathroom & 20D/20E Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 10/15/20 | Mon 10/19/20 | |
165 | 20D Bathroom & 20D/20E Kitchen | Drywall Repair & Inspections | 8 days | Tue 10/20/20 | Thu 10/29/20 | |
166 | 20D Bathroom & 20D/20E Kitchen | Texture/Paint | 5 days | Fri 10/30/20 | Thu 11/5/20 | |
167 | 20D Bathroom & 20D/20E Kitchen | Tile, Carpentry & Reconstruction | 15 days | Fri 11/6/20 | Mon 11/30/20 | |
168 | 20D Bathroom & 20D/20E Kitchen | Substantial Completion & Punchlist | 3 days | Tue 12/1/20 | Thu 12/3/20 | |
169 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | 35 days | Thu 10/15/20 | Fri 12/4/20 | ||
170 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 10/15/20 | Fri 10/16/20 | |
171 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 10/16/20 | Tue 10/20/20 | |
172 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 10/21/20 | Fri 10/30/20 | |
173 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Mon 11/2/20 | Fri 11/6/20 | |
174 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 11/9/20 | Tue 12/1/20 | |
175 | 19D Bathroom & 19D/19E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Wed 12/2/20 | Fri 12/4/20 | |
176 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | 35 days | Fri 10/16/20 | Mon 12/7/20 | ||
177 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 10/16/20 | Mon 10/19/20 | |
178 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 10/19/20 | Wed 10/21/20 | |
179 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 10/22/20 | Mon 11/2/20 | |
180 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 11/3/20 | Mon 11/9/20 | |
181 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 11/10/20 | Wed 12/2/20 | |
182 | 18D Bathroom & 18D/18E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Thu 12/3/20 | Mon 12/7/20 | |
183 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | 35 days | Mon 10/19/20 | Tue 12/8/20 | ||
184 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 10/19/20 | Tue 10/20/20 | |
185 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 10/20/20 | Thu 10/22/20 | |
186 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 10/23/20 | Tue 11/3/20 | |
187 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Wed 11/4/20 | Tue 11/10/20 | |
188 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 11/11/20 | Thu 12/3/20 | |
189 | 17D Bathroom & 17D/17E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Fri 12/4/20 | Tue 12/8/20 | |
190 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | 35 days | Tue 10/20/20 | Wed 12/9/20 | ||
191 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 10/20/20 | Wed 10/21/20 | |
192 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 10/21/20 | Fri 10/23/20 | |
193 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 10/26/20 | Wed 11/4/20 | |
194 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Thu 11/5/20 | Wed 11/11/20 | |
195 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 11/12/20 | Fri 12/4/20 | |
196 | 16D Bathroom & 16D/16E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Mon 12/7/20 | Wed 12/9/20 | |
197 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | 35 days | Wed 10/21/20 | Thu 12/10/20 | ||
198 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 10/21/20 | Thu 10/22/20 | |
199 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 10/22/20 | Mon 10/26/20 | |
200 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 10/27/20 | Thu 11/5/20 | |
201 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Fri 11/6/20 | Thu 11/12/20 | |
202 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Fri 11/13/20 | Mon 12/7/20 | |
203 | 15D Bathroom & 15D/15E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Tue 12/8/20 | Thu 12/10/20 | |
204 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | 35 days | Thu 10/22/20 | Fri 12/11/20 | ||
205 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 10/22/20 | Fri 10/23/20 | |
206 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 10/23/20 | Tue 10/27/20 | |
207 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 10/28/20 | Fri 11/6/20 | |
208 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Mon 11/9/20 | Fri 11/13/20 | |
209 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 11/16/20 | Tue 12/8/20 | |
210 | 14D Bathroom & 14D/14E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Wed 12/9/20 | Fri 12/11/20 | |
211 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | 35 days | Fri 10/23/20 | Mon 12/14/20 | ||
212 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 10/23/20 | Mon 10/26/20 | |
213 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 10/26/20 | Wed 10/28/20 | |
214 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 10/29/20 | Mon 11/9/20 | |
215 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 11/10/20 | Mon 11/16/20 | |
216 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 11/17/20 | Wed 12/9/20 | |
217 | 13D Bathroom & 13D/13E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Thu 12/10/20 | Mon 12/14/20 | |
218 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | 35 days | Mon 10/26/20 | Tue 12/15/20 | ||
219 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 10/26/20 | Tue 10/27/20 | |
220 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 10/27/20 | Thu 10/29/20 | |
221 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 10/30/20 | Tue 11/10/20 | |
222 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Wed 11/11/20 | Tue 11/17/20 | |
223 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 11/18/20 | Thu 12/10/20 | |
224 | 12D Bathroom & 12D/12E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Fri 12/11/20 | Tue 12/15/20 | |
225 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | 35 days | Tue 10/27/20 | Wed 12/16/20 | ||
226 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 10/27/20 | Wed 10/28/20 | |
227 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 10/28/20 | Fri 10/30/20 | |
228 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 11/2/20 | Wed 11/11/20 | |
229 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Thu 11/12/20 | Wed 11/18/20 | |
230 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 11/19/20 | Fri 12/11/20 | |
231 | 11D Bathroom & 11D/11E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Mon 12/14/20 | Wed 12/16/20 | |
232 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | 35 days | Wed 10/28/20 | Thu 12/17/20 | ||
233 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 10/28/20 | Thu 10/29/20 | |
234 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 10/29/20 | Mon 11/2/20 | |
235 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 11/3/20 | Thu 11/12/20 | |
236 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Fri 11/13/20 | Thu 11/19/20 | |
237 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Fri 11/20/20 | Mon 12/14/20 | |
238 | 10D Bathroom & 10D/10E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Tue 12/15/20 | Thu 12/17/20 | |
239 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | 35 days | Thu 10/29/20 | Fri 12/18/20 | ||
240 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 10/29/20 | Fri 10/30/20 | |
241 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 10/30/20 | Tue 11/3/20 | |
242 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 11/4/20 | Fri 11/13/20 | |
243 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Mon 11/16/20 | Fri 11/20/20 | |
244 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 11/23/20 | Tue 12/15/20 | |
245 | 9D Bathroom & 9D/9E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Wed 12/16/20 | Fri 12/18/20 | |
246 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | 35 days | Fri 10/30/20 | Mon 1/4/21 | ||
247 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 10/30/20 | Mon 11/2/20 | |
248 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 11/2/20 | Wed 11/4/20 | |
249 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 11/5/20 | Mon 11/16/20 | |
250 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 11/17/20 | Mon 11/23/20 | |
251 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 11/24/20 | Wed 12/16/20 | |
252 | 8D Bathroom & 8D/8E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Thu 12/17/20 | Mon 1/4/21 | |
253 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | 35 days | Mon 11/2/20 | Tue 1/5/21 | ||
254 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Mon 11/2/20 | Tue 11/3/20 | |
255 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Tue 11/3/20 | Thu 11/5/20 | |
256 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Fri 11/6/20 | Tue 11/17/20 | |
257 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Wed 11/18/20 | Tue 11/24/20 | |
258 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 11/25/20 | Thu 12/17/20 | |
259 | 7D Bathroom & 7D/7E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Fri 12/18/20 | Tue 1/5/21 | |
260 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | 35 days | Tue 11/3/20 | Wed 1/6/21 | ||
261 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Tue 11/3/20 | Wed 11/4/20 | |
262 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Wed 11/4/20 | Fri 11/6/20 | |
263 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Mon 11/9/20 | Wed 11/18/20 | |
264 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Thu 11/19/20 | Wed 11/25/20 | |
265 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Mon 11/30/20 | Fri 12/18/20 | |
266 | 6D Bathroom & 6D/6E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Mon 1/4/21 | Wed 1/6/21 | |
267 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | 35 days | Wed 11/4/20 | Thu 1/7/21 | ||
268 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Wed 11/4/20 | Thu 11/5/20 | |
269 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Thu 11/5/20 | Mon 11/9/20 | |
270 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Tue 11/10/20 | Thu 11/19/20 | |
271 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Fri 11/20/20 | Mon 11/30/20 | |
272 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Tue 12/1/20 | Mon 1/4/21 | |
273 | 5D Bathroom & 5D/5E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Tue 1/5/21 | Thu 1/7/21 | |
274 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | 35 days | Thu 11/5/20 | Fri 1/8/21 | ||
275 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Thu 11/5/20 | Fri 11/6/20 | |
276 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Fri 11/6/20 | Tue 11/10/20 | |
277 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Wed 11/11/20 | Fri 11/20/20 | |
278 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Mon 11/23/20 | Tue 12/1/20 | |
279 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Wed 12/2/20 | Tue 1/5/21 | |
280 | 4D Bathroom & 4D/4E Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Wed 1/6/21 | Fri 1/8/21 | |
281 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | 35 days | Fri 11/6/20 | Mon 1/11/21 | ||
282 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | Demoltion & Abatement | 2 days | Fri 11/6/20 | Mon 11/9/20 | |
283 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | Plumbing Replacement & Inspections | 3 days | Mon 11/9/20 | Wed 11/11/20 | |
284 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | Drywall Repair & Inspections | 8 days | Thu 11/12/20 | Mon 11/23/20 | |
285 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | Texture/Paint | 5 days | Tue 11/24/20 | Wed 12/2/20 | |
286 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | Tile, Carpentry & Reconstruction | 15 days | Thu 12/3/20 | Wed 1/6/21 | |
287 | 3 Residents Room Bathrooms & Kitchen & HVAC R#1-3 | Substantial Completion & Punchlist | 3 days | Thu 1/7/21 | Mon 1/11/21 | |
288 | 36K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen | 25 days | Fri 11/13/20 | Mon 1/4/21 | ||
289 | 36K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen | Demo drywall | 2 days | Fri 11/13/20 | Mon 11/16/20 | |
290 | 36K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen | Plumbing connection | 3 days | Tue 11/17/20 | Thu 11/19/20 | |
291 | 36K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen | Drywall Repari | 8 days | Fri 11/20/20 | Thu 12/3/20 | |
292 | 36K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen | Texture Paint | 10 days | Fri 12/4/20 | Thu 12/17/20 | |
293 | 36K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen | Substantial Completion & Punchlist | 2 days | Fri 12/18/20 | Mon 1/4/21 | |
294 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | 25 days | Fri 11/13/20 | Mon 1/4/21 | ||
295 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | Demoltion & Abatement | 2 days | Fri 11/13/20 | Mon 11/16/20 | |
296 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | Plumbing Replacement & Inspections | 2 days | Tue 11/17/20 | Wed 11/18/20 | |
297 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | Drywall Repair & Inspections | 8 days | Thu 11/19/20 | Wed 12/2/20 | |
298 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | Texture/Paint | 6 days | Thu 12/3/20 | Thu 12/10/20 | |
299 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 12/11/20 | Thu 12/17/20 | |
300 | 35K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen | Substantial Completion & Punchlist | 2 days | Fri 12/18/20 | Mon 1/4/21 | |
301 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | 25 days | Mon 11/16/20 | Tue 1/5/21 | ||
302 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | Demoltion & Abatement | 2 days | Mon 11/16/20 | Tue 11/17/20 | |
303 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 11/18/20 | Fri 11/20/20 | |
304 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | Drywall Repair & Inspections | 8 days | Mon 11/23/20 | Fri 12/4/20 | |
305 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | Texture/Paint | 5 days | Mon 12/7/20 | Fri 12/11/20 | |
306 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 12/14/20 | Fri 12/18/20 | |
307 | 34K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/4/21 | Tue 1/5/21 | |
308 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | 25 days | Mon 11/16/20 | Tue 1/5/21 | ||
309 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | Demoltion & Abatement | 2 days | Mon 11/16/20 | Tue 11/17/20 | |
310 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 11/18/20 | Fri 11/20/20 | |
311 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | Drywall Repair & Inspections | 8 days | Mon 11/23/20 | Fri 12/4/20 | |
312 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | Texture/Paint | 5 days | Mon 12/7/20 | Fri 12/11/20 | |
313 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 12/14/20 | Fri 12/18/20 | |
314 | 33K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/4/21 | Tue 1/5/21 | |
315 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | 25 days | Tue 11/17/20 | Wed 1/6/21 | ||
316 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | Demoltion & Abatement | 2 days | Tue 11/17/20 | Wed 11/18/20 | |
317 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 11/19/20 | Mon 11/23/20 | |
318 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | Drywall Repair & Inspections | 8 days | Tue 11/24/20 | Mon 12/7/20 | |
319 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | Texture/Paint | 5 days | Tue 12/8/20 | Mon 12/14/20 | |
320 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Tue 12/15/20 | Mon 1/4/21 | |
321 | 32K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen | Substantial Completion & Punchlist | 2 days | Tue 1/5/21 | Wed 1/6/21 | |
322 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | 25 days | Tue 11/17/20 | Wed 1/6/21 | ||
323 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | Demoltion & Abatement | 2 days | Tue 11/17/20 | Wed 11/18/20 | |
324 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 11/19/20 | Mon 11/23/20 | |
325 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | Drywall Repair & Inspections | 8 days | Tue 11/24/20 | Mon 12/7/20 | |
326 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | Texture/Paint | 5 days | Tue 12/8/20 | Mon 12/14/20 | |
327 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Tue 12/15/20 | Mon 1/4/21 | |
328 | 31K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen | Substantial Completion & Punchlist | 2 days | Tue 1/5/21 | Wed 1/6/21 | |
329 | 30K Bathroom & 30J/K Kitchen | 25 days | Wed 11/18/20 | Thu 1/7/21 | ||
330 | 30K Bathroom & 30J/K Kitchen | Demoltion & Abatement | 2 days | Wed 11/18/20 | Thu 11/19/20 | |
331 | 30K Bathroom & 30J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Fri 11/20/20 | Tue 11/24/20 | |
332 | 30K Bathroom & 30J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 11/25/20 | Tue 12/8/20 | |
333 | 30K Bathroom & 30J/K Kitchen | Texture/Paint | 5 days | Wed 12/9/20 | Tue 12/15/20 | |
334 | 30K Bathroom & 30J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Wed 12/16/20 | Tue 1/5/21 | |
335 | 30K Bathroom & 30J/K Kitchen | Substantial Completion & Punchlist | 2 days | Wed 1/6/21 | Thu 1/7/21 | |
336 | 29K Bathroom & 29J/K Kitchen | 25 days | Wed 11/18/20 | Thu 1/7/21 | ||
337 | 29K Bathroom & 29J/K Kitchen | Demoltion & Abatement | 2 days | Wed 11/18/20 | Thu 11/19/20 | |
338 | 29K Bathroom & 29J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Fri 11/20/20 | Tue 11/24/20 | |
339 | 29K Bathroom & 29J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 11/25/20 | Tue 12/8/20 | |
340 | 29K Bathroom & 29J/K Kitchen | Texture/Paint | 5 days | Wed 12/9/20 | Tue 12/15/20 | |
341 | 29K Bathroom & 29J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Wed 12/16/20 | Tue 1/5/21 | |
342 | 29K Bathroom & 29J/K Kitchen | Substantial Completion & Punchlist | 2 days | Wed 1/6/21 | Thu 1/7/21 | |
343 | 28K Bathroom & 28J/K Kitchen | 25 days | Thu 11/19/20 | Fri 1/8/21 | ||
344 | 28K Bathroom & 28J/K Kitchen | Demoltion & Abatement | 2 days | Thu 11/19/20 | Fri 11/20/20 | |
345 | 28K Bathroom & 28J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Mon 11/23/20 | Wed 11/25/20 | |
346 | 28K Bathroom & 28J/K Kitchen | Drywall Repair & Inspections | 8 days | Mon 11/30/20 | Wed 12/9/20 | |
347 | 28K Bathroom & 28J/K Kitchen | Texture/Paint | 5 days | Thu 12/10/20 | Wed 12/16/20 | |
348 | 28K Bathroom & 28J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Thu 12/17/20 | Wed 1/6/21 | |
349 | 28K Bathroom & 28J/K Kitchen | Substantial Completion & Punchlist | 2 days | Thu 1/7/21 | Fri 1/8/21 | |
350 | 27K Bathroom & 27J/K Kitchen | 25 days | Thu 11/19/20 | Fri 1/8/21 | ||
351 | 27K Bathroom & 27J/K Kitchen | Demoltion & Abatement | 2 days | Thu 11/19/20 | Fri 11/20/20 | |
352 | 27K Bathroom & 27J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Mon 11/23/20 | Wed 11/25/20 | |
353 | 27K Bathroom & 27J/K Kitchen | Drywall Repair & Inspections | 8 days | Mon 11/30/20 | Wed 12/9/20 | |
354 | 27K Bathroom & 27J/K Kitchen | Texture/Paint | 5 days | Thu 12/10/20 | Wed 12/16/20 | |
355 | 27K Bathroom & 27J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Thu 12/17/20 | Wed 1/6/21 | |
356 | 27K Bathroom & 27J/K Kitchen | Substantial Completion & Punchlist | 2 days | Thu 1/7/21 | Fri 1/8/21 | |
357 | 26K Bathroom & 26J/K Kitchen | 25 days | Fri 11/20/20 | Mon 1/11/21 | ||
358 | 26K Bathroom & 26J/K Kitchen | Demoltion & Abatement | 2 days | Fri 11/20/20 | Mon 11/23/20 | |
359 | 26K Bathroom & 26J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Tue 11/24/20 | Mon 11/30/20 | |
360 | 26K Bathroom & 26J/K Kitchen | Drywall Repair & Inspections | 8 days | Tue 12/1/20 | Thu 12/10/20 | |
361 | 26K Bathroom & 26J/K Kitchen | Texture/Paint | 5 days | Fri 12/11/20 | Thu 12/17/20 | |
362 | 26K Bathroom & 26J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 12/18/20 | Thu 1/7/21 | |
363 | 26K Bathroom & 26J/K Kitchen | Substantial Completion & Punchlist | 2 days | Fri 1/8/21 | Mon 1/11/21 | |
364 | 25K Bathroom & 25J/K Kitchen | 25 days | Fri 11/20/20 | Mon 1/11/21 | ||
365 | 25K Bathroom & 25J/K Kitchen | Demoltion & Abatement | 2 days | Fri 11/20/20 | Mon 11/23/20 | |
366 | 25K Bathroom & 25J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Tue 11/24/20 | Mon 11/30/20 | |
367 | 25K Bathroom & 25J/K Kitchen | Drywall Repair & Inspections | 8 days | Tue 12/1/20 | Thu 12/10/20 | |
368 | 25K Bathroom & 25J/K Kitchen | Texture/Paint | 5 days | Fri 12/11/20 | Thu 12/17/20 | |
369 | 25K Bathroom & 25J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 12/18/20 | Thu 1/7/21 | |
370 | 25K Bathroom & 25J/K Kitchen | Substantial Completion & Punchlist | 2 days | Fri 1/8/21 | Mon 1/11/21 | |
371 | 24K Bathroom & 24J/K Kitchen | 25 days | Mon 11/23/20 | Tue 1/12/21 | ||
372 | 24K Bathroom & 24J/K Kitchen | Demoltion & Abatement | 2 days | Mon 11/23/20 | Tue 11/24/20 | |
373 | 24K Bathroom & 24J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 11/25/20 | Tue 12/1/20 | |
374 | 24K Bathroom & 24J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 12/2/20 | Fri 12/11/20 | |
375 | 24K Bathroom & 24J/K Kitchen | Texture/Paint | 5 days | Mon 12/14/20 | Fri 12/18/20 | |
376 | 24K Bathroom & 24J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 1/4/21 | Fri 1/8/21 | |
377 | 24K Bathroom & 24J/K Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/11/21 | Tue 1/12/21 | |
378 | 23K Bathroom & 23J/K Kitchen | 25 days | Mon 11/23/20 | Tue 1/12/21 | ||
379 | 23K Bathroom & 23J/K Kitchen | Demoltion & Abatement | 2 days | Mon 11/23/20 | Tue 11/24/20 | |
380 | 23K Bathroom & 23J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 11/25/20 | Tue 12/1/20 | |
381 | 23K Bathroom & 23J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 12/2/20 | Fri 12/11/20 | |
382 | 23K Bathroom & 23J/K Kitchen | Texture/Paint | 5 days | Mon 12/14/20 | Fri 12/18/20 | |
383 | 23K Bathroom & 23J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 1/4/21 | Fri 1/8/21 | |
384 | 23K Bathroom & 23J/K Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/11/21 | Tue 1/12/21 | |
385 | 22K Bathroom & 22J/K Kitchen | 25 days | Tue 11/24/20 | Wed 1/13/21 | ||
386 | 22K Bathroom & 22J/K Kitchen | Demoltion & Abatement | 2 days | Tue 11/24/20 | Wed 11/25/20 | |
387 | 22K Bathroom & 22J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Mon 11/30/20 | Wed 12/2/20 | |
388 | 22K Bathroom & 22J/K Kitchen | Drywall Repair & Inspections | 8 days | Thu 12/3/20 | Mon 12/14/20 | |
389 | 22K Bathroom & 22J/K Kitchen | Texture/Paint | 5 days | Tue 12/15/20 | Mon 1/4/21 | |
390 | 22K Bathroom & 22J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Tue 1/5/21 | Mon 1/11/21 | |
391 | 22K Bathroom & 22J/K Kitchen | Substantial Completion & Punchlist | 2 days | Tue 1/12/21 | Wed 1/13/21 | |
392 | 21K Bathroom & 21J/K Kitchen | 25 days | Tue 11/24/20 | Wed 1/13/21 | ||
393 | 21K Bathroom & 21J/K Kitchen | Demoltion & Abatement | 2 days | Tue 11/24/20 | Wed 11/25/20 | |
394 | 21K Bathroom & 21J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Mon 11/30/20 | Wed 12/2/20 | |
395 | 21K Bathroom & 21J/K Kitchen | Drywall Repair & Inspections | 8 days | Thu 12/3/20 | Mon 12/14/20 | |
396 | 21K Bathroom & 21J/K Kitchen | Texture/Paint | 5 days | Tue 12/15/20 | Mon 1/4/21 | |
397 | 21K Bathroom & 21J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Tue 1/5/21 | Mon 1/11/21 | |
398 | 21K Bathroom & 21J/K Kitchen | Substantial Completion & Punchlist | 2 days | Tue 1/12/21 | Wed 1/13/21 | |
399 | 20K Bathroom & 20J/K Kitchen | 25 days | Wed 11/25/20 | Thu 1/14/21 | ||
400 | 20K Bathroom & 20J/K Kitchen | Demoltion & Abatement | 2 days | Wed 11/25/20 | Mon 11/30/20 | |
401 | 20K Bathroom & 20J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Tue 12/1/20 | Thu 12/3/20 | |
402 | 20K Bathroom & 20J/K Kitchen | Drywall Repair & Inspections | 8 days | Fri 12/4/20 | Tue 12/15/20 | |
403 | 20K Bathroom & 20J/K Kitchen | Texture/Paint | 5 days | Wed 12/16/20 | Tue 1/5/21 | |
404 | 20K Bathroom & 20J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Wed 1/6/21 | Tue 1/12/21 | |
405 | 20K Bathroom & 20J/K Kitchen | Substantial Completion & Punchlist | 2 days | Wed 1/13/21 | Thu 1/14/21 | |
406 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | 25 days | Wed 11/25/20 | Thu 1/14/21 | ||
407 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | Demoltion & Abatement | 2 days | Wed 11/25/20 | Mon 11/30/20 | |
408 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | Plumbing Replacement & Inspections | 3 days | Tue 12/1/20 | Thu 12/3/20 | |
409 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | Drywall Repair & Inspections | 8 days | Fri 12/4/20 | Tue 12/15/20 | |
410 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | Texture/Paint | 5 days | Wed 12/16/20 | Tue 1/5/21 | |
411 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Wed 1/6/21 | Tue 1/12/21 | |
412 | 19K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen | Substantial Completion & Punchlist | 2 days | Wed 1/13/21 | Thu 1/14/21 | |
413 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | 25 days | Mon 11/30/20 | Fri 1/15/21 | ||
414 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | Demoltion & Abatement | 2 days | Mon 11/30/20 | Tue 12/1/20 | |
415 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 12/2/20 | Fri 12/4/20 | |
416 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | Drywall Repair & Inspections | 8 days | Mon 12/7/20 | Wed 12/16/20 | |
417 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | Texture/Paint | 5 days | Thu 12/17/20 | Wed 1/6/21 | |
418 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Thu 1/7/21 | Wed 1/13/21 | |
419 | 18K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen | Substantial Completion & Punchlist | 2 days | Thu 1/14/21 | Fri 1/15/21 | |
420 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | 25 days | Mon 11/30/20 | Fri 1/15/21 | ||
421 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | Demoltion & Abatement | 2 days | Mon 11/30/20 | Tue 12/1/20 | |
422 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 12/2/20 | Fri 12/4/20 | |
423 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | Drywall Repair & Inspections | 8 days | Mon 12/7/20 | Wed 12/16/20 | |
424 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | Texture/Paint | 5 days | Thu 12/17/20 | Wed 1/6/21 | |
425 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | Tile, Carpentry & Reconstruction | 5 days | Thu 1/7/21 | Wed 1/13/21 | |
426 | 17K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen | Substantial Completion & Punchlist | 2 days | Thu 1/14/21 | Fri 1/15/21 | |
427 | 16K Bathroom & 16J/K Kitchen | 25 days | Tue 12/1/20 | Mon 1/18/21 | ||
428 | 16K Bathroom & 16J/K Kitchen | Demoltion & Abatement | 2 days | Tue 12/1/20 | Wed 12/2/20 | |
429 | 16K Bathroom & 16J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 12/3/20 | Mon 12/7/20 | |
430 | 16K Bathroom & 16J/K Kitchen | Drywall Repair & Inspections | 8 days | Tue 12/8/20 | Thu 12/17/20 | |
431 | 16K Bathroom & 16J/K Kitchen | Texture/Paint | 5 days | Fri 12/18/20 | Thu 1/7/21 | |
432 | 16K Bathroom & 16J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 1/8/21 | Thu 1/14/21 | |
433 | 16K Bathroom & 16J/K Kitchen | Substantial Completion & Punchlist | 2 days | Fri 1/15/21 | Mon 1/18/21 | |
434 | 15K Bathroom & 15J/K Kitchen | 25 days | Tue 12/1/20 | Mon 1/18/21 | ||
435 | 15K Bathroom & 15J/K Kitchen | Demoltion & Abatement | 2 days | Tue 12/1/20 | Wed 12/2/20 | |
436 | 15K Bathroom & 15J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 12/3/20 | Mon 12/7/20 | |
437 | 15K Bathroom & 15J/K Kitchen | Drywall Repair & Inspections | 8 days | Tue 12/8/20 | Thu 12/17/20 | |
438 | 15K Bathroom & 15J/K Kitchen | Texture/Paint | 5 days | Fri 12/18/20 | Thu 1/7/21 | |
439 | 15K Bathroom & 15J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 1/8/21 | Thu 1/14/21 | |
440 | 15K Bathroom & 15J/K Kitchen | Substantial Completion & Punchlist | 2 days | Fri 1/15/21 | Mon 1/18/21 | |
441 | 14K Bathroom & 14J/K Kitchen | 25 days | Wed 12/2/20 | Tue 1/19/21 | ||
442 | 14K Bathroom & 14J/K Kitchen | Demoltion & Abatement | 2 days | Wed 12/2/20 | Thu 12/3/20 | |
443 | 14K Bathroom & 14J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Fri 12/4/20 | Tue 12/8/20 | |
444 | 14K Bathroom & 14J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 12/9/20 | Fri 12/18/20 | |
445 | 14K Bathroom & 14J/K Kitchen | Texture/Paint | 5 days | Mon 1/4/21 | Fri 1/8/21 | |
446 | 14K Bathroom & 14J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 1/11/21 | Fri 1/15/21 | |
447 | 14K Bathroom & 14J/K Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/18/21 | Tue 1/19/21 | |
448 | 13K Bathroom & 13J/K Kitchen | 25 days | Wed 12/2/20 | Tue 1/19/21 | ||
449 | 13K Bathroom & 13J/K Kitchen | Demoltion & Abatement | 2 days | Wed 12/2/20 | Thu 12/3/20 | |
450 | 13K Bathroom & 13J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Fri 12/4/20 | Tue 12/8/20 | |
451 | 13K Bathroom & 13J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 12/9/20 | Fri 12/18/20 | |
452 | 13K Bathroom & 13J/K Kitchen | Texture/Paint | 5 days | Mon 1/4/21 | Fri 1/8/21 | |
453 | 13K Bathroom & 13J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 1/11/21 | Fri 1/15/21 | |
454 | 13K Bathroom & 13J/K Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/18/21 | Tue 1/19/21 | |
455 | 12K Bathroom & 12J/K Kitchen | 25 days | Thu 12/3/20 | Wed 1/20/21 | ||
456 | 12K Bathroom & 12J/K Kitchen | Demoltion & Abatement | 2 days | Thu 12/3/20 | Fri 12/4/20 | |
457 | 12K Bathroom & 12J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Mon 12/7/20 | Wed 12/9/20 | |
458 | 12K Bathroom & 12J/K Kitchen | Drywall Repair & Inspections | 8 days | Thu 12/10/20 | Mon 1/4/21 | |
459 | 12K Bathroom & 12J/K Kitchen | Texture/Paint | 5 days | Tue 1/5/21 | Mon 1/11/21 | |
460 | 12K Bathroom & 12J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Tue 1/12/21 | Mon 1/18/21 | |
461 | 12K Bathroom & 12J/K Kitchen | Substantial Completion & Punchlist | 2 days | Tue 1/19/21 | Wed 1/20/21 | |
462 | 11K Bathroom & 11J/K Kitchen | 25 days | Thu 12/3/20 | Wed 1/20/21 | ||
463 | 11K Bathroom & 11J/K Kitchen | Demoltion & Abatement | 2 days | Thu 12/3/20 | Fri 12/4/20 | |
464 | 11K Bathroom & 11J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Mon 12/7/20 | Wed 12/9/20 | |
465 | 11K Bathroom & 11J/K Kitchen | Drywall Repair & Inspections | 8 days | Thu 12/10/20 | Mon 1/4/21 | |
466 | 11K Bathroom & 11J/K Kitchen | Texture/Paint | 5 days | Tue 1/5/21 | Mon 1/11/21 | |
467 | 11K Bathroom & 11J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Tue 1/12/21 | Mon 1/18/21 | |
468 | 11K Bathroom & 11J/K Kitchen | Substantial Completion & Punchlist | 2 days | Tue 1/19/21 | Wed 1/20/21 | |
469 | 10K Bathroom & 10J/K Kitchen | 25 days | Fri 12/4/20 | Thu 1/21/21 | ||
470 | 10K Bathroom & 10J/K Kitchen | Demoltion & Abatement | 2 days | Fri 12/4/20 | Mon 12/7/20 | |
471 | 10K Bathroom & 10J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Tue 12/8/20 | Thu 12/10/20 | |
472 | 10K Bathroom & 10J/K Kitchen | Drywall Repair & Inspections | 8 days | Fri 12/11/20 | Tue 1/5/21 | |
473 | 10K Bathroom & 10J/K Kitchen | Texture/Paint | 5 days | Wed 1/6/21 | Tue 1/12/21 | |
474 | 10K Bathroom & 10J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Wed 1/13/21 | Tue 1/19/21 | |
475 | 10K Bathroom & 10J/K Kitchen | Substantial Completion & Punchlist | 2 days | Wed 1/20/21 | Thu 1/21/21 | |
476 | 9K Bathroom & 9J/K Kitchen | 25 days | Fri 12/4/20 | Thu 1/21/21 | ||
477 | 9K Bathroom & 9J/K Kitchen | Demoltion & Abatement | 2 days | Fri 12/4/20 | Mon 12/7/20 | |
478 | 9K Bathroom & 9J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Tue 12/8/20 | Thu 12/10/20 | |
479 | 9K Bathroom & 9J/K Kitchen | Drywall Repair & Inspections | 8 days | Fri 12/11/20 | Tue 1/5/21 | |
480 | 9K Bathroom & 9J/K Kitchen | Texture/Paint | 5 days | Wed 1/6/21 | Tue 1/12/21 | |
481 | 9K Bathroom & 9J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Wed 1/13/21 | Tue 1/19/21 | |
482 | 9K Bathroom & 9J/K Kitchen | Substantial Completion & Punchlist | 2 days | Wed 1/20/21 | Thu 1/21/21 | |
483 | 8K Bathroom & 8J/K Kitchen | 25 days | Mon 12/7/20 | Fri 1/22/21 | ||
484 | 8K Bathroom & 8J/K Kitchen | Demoltion & Abatement | 2 days | Mon 12/7/20 | Tue 12/8/20 | |
485 | 8K Bathroom & 8J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 12/9/20 | Fri 12/11/20 | |
486 | 8K Bathroom & 8J/K Kitchen | Drywall Repair & Inspections | 8 days | Mon 12/14/20 | Wed 1/6/21 | |
487 | 8K Bathroom & 8J/K Kitchen | Texture/Paint | 5 days | Thu 1/7/21 | Wed 1/13/21 | |
488 | 8K Bathroom & 8J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Thu 1/14/21 | Wed 1/20/21 | |
489 | 8K Bathroom & 8J/K Kitchen | Substantial Completion & Punchlist | 2 days | Thu 1/21/21 | Fri 1/22/21 | |
490 | 7K Bathroom & 7J/K Kitchen | 25 days | Mon 12/7/20 | Fri 1/22/21 | ||
491 | 7K Bathroom & 7J/K Kitchen | Demoltion & Abatement | 2 days | Mon 12/7/20 | Tue 12/8/20 | |
492 | 7K Bathroom & 7J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Wed 12/9/20 | Fri 12/11/20 | |
493 | 7K Bathroom & 7J/K Kitchen | Drywall Repair & Inspections | 8 days | Mon 12/14/20 | Wed 1/6/21 | |
494 | 7K Bathroom & 7J/K Kitchen | Texture/Paint | 5 days | Thu 1/7/21 | Wed 1/13/21 | |
495 | 7K Bathroom & 7J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Thu 1/14/21 | Wed 1/20/21 | |
496 | 7K Bathroom & 7J/K Kitchen | Substantial Completion & Punchlist | 2 days | Thu 1/21/21 | Fri 1/22/21 | |
497 | 6K Bathroom & 6J/K Kitchen | 25 days | Tue 12/8/20 | Mon 1/25/21 | ||
498 | 6K Bathroom & 6J/K Kitchen | Demoltion & Abatement | 2 days | Tue 12/8/20 | Wed 12/9/20 | |
499 | 6K Bathroom & 6J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 12/10/20 | Mon 12/14/20 | |
500 | 6K Bathroom & 6J/K Kitchen | Drywall Repair & Inspections | 8 days | Tue 12/15/20 | Thu 1/7/21 | |
501 | 6K Bathroom & 6J/K Kitchen | Texture/Paint | 5 days | Fri 1/8/21 | Thu 1/14/21 | |
502 | 6K Bathroom & 6J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 1/15/21 | Thu 1/21/21 | |
503 | 6K Bathroom & 6J/K Kitchen | Substantial Completion & Punchlist | 2 days | Fri 1/22/21 | Mon 1/25/21 | |
504 | 5K Bathroom & 5J/K Kitchen | 25 days | Tue 12/8/20 | Mon 1/25/21 | ||
505 | 5K Bathroom & 5J/K Kitchen | Demoltion & Abatement | 2 days | Tue 12/8/20 | Wed 12/9/20 | |
506 | 5K Bathroom & 5J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Thu 12/10/20 | Mon 12/14/20 | |
507 | 5K Bathroom & 5J/K Kitchen | Drywall Repair & Inspections | 8 days | Tue 12/15/20 | Thu 1/7/21 | |
508 | 5K Bathroom & 5J/K Kitchen | Texture/Paint | 5 days | Fri 1/8/21 | Thu 1/14/21 | |
509 | 5K Bathroom & 5J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Fri 1/15/21 | Thu 1/21/21 | |
510 | 5K Bathroom & 5J/K Kitchen | Substantial Completion & Punchlist | 2 days | Fri 1/22/21 | Mon 1/25/21 | |
511 | 4K Bathroom & 4J/K Kitchen | 25 days | Wed 12/9/20 | Tue 1/26/21 | ||
512 | 4K Bathroom & 4J/K Kitchen | Demoltion & Abatement | 2 days | Wed 12/9/20 | Thu 12/10/20 | |
513 | 4K Bathroom & 4J/K Kitchen | Plumbing Replacement & Inspections | 3 days | Fri 12/11/20 | Tue 12/15/20 | |
514 | 4K Bathroom & 4J/K Kitchen | Drywall Repair & Inspections | 8 days | Wed 12/16/20 | Fri 1/8/21 | |
515 | 4K Bathroom & 4J/K Kitchen | Texture/Paint | 5 days | Mon 1/11/21 | Fri 1/15/21 | |
516 | 4K Bathroom & 4J/K Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 1/18/21 | Fri 1/22/21 | |
517 | 4K Bathroom & 4J/K Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/25/21 | Tue 1/26/21 | |
518 | 3E Bathroom & 3D/E Kitchen | 25 days | Wed 12/9/20 | Tue 1/26/21 | ||
519 | 3E Bathroom & 3D/E Kitchen | Demoltion & Abatement | 2 days | Wed 12/9/20 | Thu 12/10/20 | |
520 | 3E Bathroom & 3D/E Kitchen | Plumbing Replacement & Inspections | 3 days | Fri 12/11/20 | Tue 12/15/20 | |
521 | 3E Bathroom & 3D/E Kitchen | Drywall Repair & Inspections | 8 days | Wed 12/16/20 | Fri 1/8/21 | |
522 | 3E Bathroom & 3D/E Kitchen | Texture/Paint | 5 days | Mon 1/11/21 | Fri 1/15/21 | |
523 | 3E Bathroom & 3D/E Kitchen | Tile, Carpentry & Reconstruction | 5 days | Mon 1/18/21 | Fri 1/22/21 | |
524 | 3E Bathroom & 3D/E Kitchen | Substantial Completion & Punchlist | 2 days | Mon 1/25/21 | Tue 1/26/21 | |
525 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | 17 days | Thu 12/10/20 | Fri 1/15/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E | |
526 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Drywall Abatement | 13 days | Thu 12/10/20 | Mon 1/11/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
527 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Demolish old piping-Riser Outage | 13 days | Fri 12/11/20 | Tue 1/12/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
528 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Install New Piping | 13 days | Fri 12/11/20 | Tue 1/12/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
529 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Test/Insulate | 13 days | Mon 12/14/20 | Wed 1/13/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
530 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Restore Service | 1 day | Wed 1/13/21 | Wed 1/13/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
531 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Drywall Repair/Paint | 14 days | Mon 12/14/20 | Thu 1/14/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
532 | Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE | Substantial Completion | 1 day | Fri 1/15/21 | Fri 1/15/21 | 42A, 42B, 41C, 41 D, 41E, 40C, 40D, 40E, 39C,39D, 39E, 38C, 38D, 38E, 37C, 37D, 37E, 36C, 36D, 36E, 35C, 35D, 35E, 34C, 34D, 34E, 33C, 33D, 33E, 32C, 32D, 32E, 31C, 31D, 31E, 30C, 30D, 30E, 29C, 29D, 29E, 28C, 28D, 28E, 27C, 27D, 27E, 26C, 26D, 26E, 25C, 25D, 25E, 24C, 24D, 24E, 23C. 23D, 23E, 22C, 22D, 22E, 21C, 21D, 21E, 20C, 20D, 20E, 19C, 19D, 19E, 18C, 18D, 18E, 17C, 17D,17E, 16C, 16D, 16E, 15C, 15D, 15E, 14C, 14D, 14E, 13C, 13D, 13E, 12C, 12D, 12E, 11C, 11D, 11E, 10C, 10 D, 10E, 9C, 9D, 9E, 8C, 8D, 8E, 7C, 7D, 7E, 6C, 6D, 6E, 5C, 5D, 5E, 4C, 4D, 4E, 3C, 3D, 3E |
533 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | 12 days | Tue 1/12/21 | Wed 1/27/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L | |
534 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Drywall Abatement | 8 days | Tue 1/12/21 | Thu 1/21/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
535 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Demolish old piping-Riser Outage | 8 days | Wed 1/13/21 | Fri 1/22/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
536 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Install New Piping | 8 days | Wed 1/13/21 | Fri 1/22/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
537 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Test/Insulate | 8 days | Thu 1/14/21 | Mon 1/25/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
538 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Restore Service | 1 day | Mon 1/25/21 | Mon 1/25/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
539 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Drywall Repair/Paint | 9 days | Thu 1/14/21 | Tue 1/26/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
540 | Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE | Substantial Completion | 1 day | Wed 1/27/21 | Wed 1/27/21 | 42C, 41J, 41K, 41L, 40J, 40K, 40L, 39J, 39K, 39L, 38J, 38K, 38L, 37J, 37K, 37L, 36J, 36K, 36L, 35J, 35K, 35L, 34J, 34K, 34L, 33J, 33K, 33L, 32J, 32K, 32L, 31J, 31K, 31L, 30J, 30K, 30L, 29J, 29K, 29L, 28J, 28K, 28L, 27J, 27K, 27L, 26J, 26K, 26L, 25J, 25K, 25L, 24J, 24K, 24L, 23J, 23K, 23L, 22J, 22K, 22L, 21J, 21K, 21L, 20J, 20K, 20L, 19J, 19K, 19L, 18J, 18K, 18L |
541 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | 9 days | Fri 1/22/21 | Wed 2/3/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D | |
542 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Drywall Abatement | 5 days | Fri 1/22/21 | Thu 1/28/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
543 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Demolish old piping-Riser Outage | 5 days | Mon 1/25/21 | Fri 1/29/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
544 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Install New Piping | 5 days | Mon 1/25/21 | Fri 1/29/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
545 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Test/Insulate | 5 days | Tue 1/26/21 | Mon 2/1/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
546 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Restore Service | 1 day | Mon 2/1/21 | Mon 2/1/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
547 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Drywall Repair/Paint | 6 days | Tue 1/26/21 | Tue 2/2/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
548 | Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE | Substantial Completion | 1 day | Wed 2/3/21 | Wed 2/3/21 | 17J, 17K, 17L, 16J, 16K, 16L, 15J, 15K, 15L, 14J, 14K, 14L, 13J, 13K, 13L, 12J, 12K, 12L, 11J, 11K, 11L, 10J, 10K, 10L, 9J, 9K, 9L, 8J, 8K, 8L, 7J, 7K, 7L, 6J, 6K, 6L, 5J, 5K, 5L, 4J, 4K, 4L, 3D |
549 | Riser #2-1 Replacement, E Living Room 41st-3rd | 17 days | Fri 1/29/21 | Mon 2/22/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E | |
550 | Riser #2-1 Replacement, E Living Room 41st-3rd | Drywall Abatement | 13 days | Fri 1/29/21 | Tue 2/16/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
551 | Riser #2-1 Replacement, E Living Room 41st-3rd | Demolish old piping-Riser Outage | 13 days | Mon 2/1/21 | Wed 2/17/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
552 | Riser #2-1 Replacement, E Living Room 41st-3rd | Install New Piping | 13 days | Mon 2/1/21 | Wed 2/17/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
553 | Riser #2-1 Replacement, E Living Room 41st-3rd | Test/Insulate | 13 days | Tue 2/2/21 | Thu 2/18/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
554 | Riser #2-1 Replacement, E Living Room 41st-3rd | Restore Service | 1 day | Thu 2/18/21 | Thu 2/18/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
555 | Riser #2-1 Replacement, E Living Room 41st-3rd | Drywall Repair/Paint | 14 days | Tue 2/2/21 | Fri 2/19/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
556 | Riser #2-1 Replacement, E Living Room 41st-3rd | Substantial Completion | 1 day | Mon 2/22/21 | Mon 2/22/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
557 | Riser #2-3 Replacement, G Living Room 41st-3rd | 17 days | Wed 2/17/21 | Thu 3/11/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, | |
558 | Riser #2-3 Replacement, G Living Room 41st-3rd | Drywall Abatement | 13 days | Wed 2/17/21 | Fri 3/5/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
559 | Riser #2-3 Replacement, G Living Room 41st-3rd | Demolish old piping-Riser Outage | 13 days | Thu 2/18/21 | Mon 3/8/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
560 | Riser #2-3 Replacement, G Living Room 41st-3rd | Install New Piping | 13 days | Thu 2/18/21 | Mon 3/8/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
561 | Riser #2-3 Replacement, G Living Room 41st-3rd | Test/Insulate | 13 days | Fri 2/19/21 | Tue 3/9/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
562 | Riser #2-3 Replacement, G Living Room 41st-3rd | Restore Service | 1 day | Tue 3/9/21 | Tue 3/9/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
563 | Riser #2-3 Replacement, G Living Room 41st-3rd | Drywall Repair/Paint | 14 days | Fri 2/19/21 | Wed 3/10/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
564 | Riser #2-3 Replacement, G Living Room 41st-3rd | Substantial Completion | 1 day | Thu 3/11/21 | Thu 3/11/21 | 42B, 41G, 40G, 39G, 38G, 37G, 36G, 35G, 34G, 33G, 32G, 31G, 30G, 29G, 28G, 27G, 26G, 25G, 24G, 23G, 22G, 21G, 20G, 19G, 18G, 17G, 16G, 15G, 14G, 13G, 12G, 11G, 10G, 9G, 8G, 7G, 6G, 5G, 4G, |
565 | Riser #2-4 Replacement, H Living 41st-3rd | 17 days | Mon 3/8/21 | Tue 3/30/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B | |
566 | Riser #2-4 Replacement, H Living 41st-3rd | Drywall Abatement | 13 days | Mon 3/8/21 | Wed 3/24/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
567 | Riser #2-4 Replacement, H Living 41st-3rd | Demolish old piping-Riser Outage | 13 days | Tue 3/9/21 | Thu 3/25/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
568 | Riser #2-4 Replacement, H Living 41st-3rd | Install New Piping | 13 days | Tue 3/9/21 | Thu 3/25/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
569 | Riser #2-4 Replacement, H Living 41st-3rd | Test/Insulate | 13 days | Wed 3/10/21 | Fri 3/26/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
570 | Riser #2-4 Replacement, H Living 41st-3rd | Restore Service | 1 day | Fri 3/26/21 | Fri 3/26/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
571 | Riser #2-4 Replacement, H Living 41st-3rd | Drywall Repair/Paint | 14 days | Wed 3/10/21 | Mon 3/29/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
572 | Riser #2-4 Replacement, H Living 41st-3rd | Substantial Completion | 1 day | Tue 3/30/21 | Tue 3/30/21 | 42C, 41H, 40H, 39H, 38H, 37H, 36H, 35H, 34H, 33H, 32H, 31H, 30H, 29H, 28H, 27H, 26H, 25H, 24H, 23H, 22H, 21H, 20H, 19H, 18H, 17H, 16H, 15H, 14H, 13H, 12H, 11H, 10H, 9H, 8H, 7H, 6H, 5H, 4H, 3B |
573 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | 9 days | Thu 3/25/21 | Tue 4/6/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, | |
574 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Drywall Abatement | 5 days | Thu 3/25/21 | Wed 3/31/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
575 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Demolish old piping-Riser Outage | 5 days | Fri 3/26/21 | Thu 4/1/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
576 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Install New Piping | 5 days | Fri 3/26/21 | Thu 4/1/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
577 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Test/Insulate | 5 days | Mon 3/29/21 | Fri 4/2/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
578 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Restore Service | 1 day | Fri 4/2/21 | Fri 4/2/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
579 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Drywall Repair/Paint | 6 days | Mon 3/29/21 | Mon 4/5/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
580 | Riser #4-4 Replacement, A/B Bathrooms 17th-3rd | Substantial Completion | 1 day | Tue 4/6/21 | Tue 4/6/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
581 | Riser #2-6 Replacement, J Living Room 41st-3rd | 17 days | Thu 4/1/21 | Fri 4/23/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J | |
582 | Riser #2-6 Replacement, J Living Room 41st-3rd | Drywall Abatement | 13 days | Thu 4/1/21 | Mon 4/19/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
583 | Riser #2-6 Replacement, J Living Room 41st-3rd | Demolish old piping-Riser Outage | 13 days | Fri 4/2/21 | Tue 4/20/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
584 | Riser #2-6 Replacement, J Living Room 41st-3rd | Install New Piping | 13 days | Fri 4/2/21 | Tue 4/20/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
585 | Riser #2-6 Replacement, J Living Room 41st-3rd | Test/Insulate | 13 days | Mon 4/5/21 | Wed 4/21/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
586 | Riser #2-6 Replacement, J Living Room 41st-3rd | Restore Service | 1 day | Wed 4/21/21 | Wed 4/21/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
587 | Riser #2-6 Replacement, J Living Room 41st-3rd | Drywall Repair/Paint | 14 days | Mon 4/5/21 | Thu 4/22/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
588 | Riser #2-6 Replacement, J Living Room 41st-3rd | Substantial Completion | 1 day | Fri 4/23/21 | Fri 4/23/21 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J, 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J |
589 | Riser #4-3 Replacement, A Living Room 17th-3rd | 9 days | Tue 4/20/21 | Fri 4/30/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, | |
590 | Riser #4-3 Replacement, A Living Room 17th-3rd | Drywall Abatement | 4 days | Tue 4/20/21 | Fri 4/23/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
591 | Riser #4-3 Replacement, A Living Room 17th-3rd | Demolish old piping-Riser Outage | 4 days | Wed 4/21/21 | Mon 4/26/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
592 | Riser #4-3 Replacement, A Living Room 17th-3rd | Install New Piping | 4 days | Wed 4/21/21 | Mon 4/26/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
593 | Riser #4-3 Replacement, A Living Room 17th-3rd | Test/Insulate | 5 days | Thu 4/22/21 | Wed 4/28/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
594 | Riser #4-3 Replacement, A Living Room 17th-3rd | Restore Service | 1 day | Tue 4/27/21 | Tue 4/27/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
595 | Riser #4-3 Replacement, A Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Thu 4/22/21 | Thu 4/29/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
596 | Riser #4-3 Replacement, A Living Room 17th-3rd | Substantial Completion | 1 day | Fri 4/30/21 | Fri 4/30/21 | 17A, 16A, 15A, 14A, 13A, 12A, 11A, 10A, 9A, 8A, 7A, 6A, 5A, 4A, |
597 | Riser #4-1 Replacement, C Living Room 17th-3rd | 9 days | Mon 4/26/21 | Thu 5/6/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, | |
598 | Riser #4-1 Replacement, C Living Room 17th-3rd | Drywall Abatement | 4 days | Mon 4/26/21 | Thu 4/29/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
599 | Riser #4-1 Replacement, C Living Room 17th-3rd | Demolish old piping-Riser Outage | 4 days | Tue 4/27/21 | Fri 4/30/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
600 | Riser #4-1 Replacement, C Living Room 17th-3rd | Install New Piping | 4 days | Tue 4/27/21 | Fri 4/30/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
601 | Riser #4-1 Replacement, C Living Room 17th-3rd | Test/Insulate | 5 days | Wed 4/28/21 | Tue 5/4/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
602 | Riser #4-1 Replacement, C Living Room 17th-3rd | Restore Service | 1 day | Mon 5/3/21 | Mon 5/3/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
603 | Riser #4-1 Replacement, C Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Wed 4/28/21 | Wed 5/5/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
604 | Riser #4-1 Replacement, C Living Room 17th-3rd | Substantial Completion | 1 day | Thu 5/6/21 | Thu 5/6/21 | 17C, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C, |
605 | Riser #3-1 Replacement, C Living Room 41st-18th | 12 days | Fri 4/30/21 | Mon 5/17/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C | |
606 | Riser #3-1 Replacement, C Living Room 41st-18th | Drywall Abatement | 8 days | Fri 4/30/21 | Tue 5/11/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
607 | Riser #3-1 Replacement, C Living Room 41st-18th | Demolish old piping-Riser Outage | 8 days | Mon 5/3/21 | Wed 5/12/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
608 | Riser #3-1 Replacement, C Living Room 41st-18th | Install New Piping | 8 days | Mon 5/3/21 | Wed 5/12/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
609 | Riser #3-1 Replacement, C Living Room 41st-18th | Test/Insulate | 8 days | Tue 5/4/21 | Thu 5/13/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
610 | Riser #3-1 Replacement, C Living Room 41st-18th | Restore Service | 1 day | Thu 5/13/21 | Thu 5/13/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
611 | Riser #3-1 Replacement, C Living Room 41st-18th | Drywall Repair/Paint | 9 days | Tue 5/4/21 | Fri 5/14/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
612 | Riser #3-1 Replacement, C Living Room 41st-18th | Substantial Completion | 1 day | Mon 5/17/21 | Mon 5/17/21 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C |
613 | Riser Valve Installation [SHOULDER #2] | 10 days | Wed 5/12/21 | Tue 5/25/21 | 42A, 42D, 41A, 41B, 41K, 41L, 17A, 17l, 17M, 17N | |
614 | Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER] | 18 days | Thu 5/20/21 | Tue 6/15/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C | |
615 | 0 | Drywall Abatement | 13 days | Thu 5/20/21 | Tue 6/8/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
616 | 0 | Demolish old piping-Riser Outage | 13 days | Fri 5/21/21 | Wed 6/9/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
617 | 0 | Install New Piping | 13 days | Fri 5/21/21 | Wed 6/9/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
618 | 0 | Test/Insulate | 13 days | Mon 5/24/21 | Thu 6/10/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
619 | 0 | Restore Service | 1 day | Fri 6/11/21 | Fri 6/11/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
620 | 0 | Drywall Repair/Paint | 14 days | Tue 5/25/21 | Mon 6/14/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
621 | 0 | Substantial Completion | 1 day | Tue 6/15/21 | Tue 6/15/21 | 42C, 41H, 41I, 40H, 40I, 39H, 39I, 38H, 38I, 37H, 37I, 36H, 36I, 35H, 35I, 34H, 34I, 33H, 33I, 32H, 32I, 31H, 31I, 30H, 30I, 29H, 29I, 28H, 28I, 27H, 27I, 26H, 26I, 25H, 25I, 24H, 24I, 23H, 23I, 22H, 22I, 21H, 21I, 20H, 20I, 19H, 19I, 18H, 18I, 17H, 17I, 16H, 16I, 15H, 15I, 14H, 14I, 13H, 13I, 12H, 12I, 11H, 11I, 10H, 10I, 9H, 9I, 8H, 8I, 7H, 7I, 6H, 6I, 5H, 5I, 4H, 4I, 3B, 3C |
622 | Riser #3-2 Replacement, B Living Room 41st-18th | 12 days | Wed 6/9/21 | Thu 6/24/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B | |
623 | Riser #3-2 Replacement, B Living Room 41st-18th | Drywall Abatement | 8 days | Wed 6/9/21 | Fri 6/18/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
624 | Riser #3-2 Replacement, B Living Room 41st-18th | Demolish old piping-Riser Outage | 8 days | Thu 6/10/21 | Mon 6/21/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
625 | Riser #3-2 Replacement, B Living Room 41st-18th | Install New Piping | 8 days | Thu 6/10/21 | Mon 6/21/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
626 | Riser #3-2 Replacement, B Living Room 41st-18th | Test/Insulate | 8 days | Fri 6/11/21 | Tue 6/22/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
627 | Riser #3-2 Replacement, B Living Room 41st-18th | Restore Service | 1 day | Tue 6/22/21 | Tue 6/22/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
628 | Riser #3-2 Replacement, B Living Room 41st-18th | Drywall Repair/Paint | 9 days | Fri 6/11/21 | Wed 6/23/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
629 | Riser #3-2 Replacement, B Living Room 41st-18th | Substantial Completion | 1 day | Thu 6/24/21 | Thu 6/24/21 | 42A, 41A, 41B, 40A, 40B, 39A, 39B, 38A, 38B, 37A, 37B, 36A, 36B, 35A, 35B, 34A, 34B, 33A, 33B, 32A, 32B, 31A, 31B, 30A, 30B, 29A, 29B, 28A, 28B, 27A, 27B, 26A, 26B, 25A, 25B, 24A, 24B, 23A, 23B, 22A, 22B, 21A, 21B, 20A, 20B, 19A, 19B, 18A, 18B |
630 | Riser #4-2 Replacement, B Living Room 17th-3rd | 9 days | Mon 6/21/21 | Thu 7/1/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B | |
631 | Riser #4-2 Replacement, B Living Room 17th-3rd | Drywall Abatement | 4 days | Mon 6/21/21 | Thu 6/24/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
632 | Riser #4-2 Replacement, B Living Room 17th-3rd | Demolish old piping-Riser Outage | 4 days | Tue 6/22/21 | Fri 6/25/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
633 | Riser #4-2 Replacement, B Living Room 17th-3rd | Install New Piping | 4 days | Tue 6/22/21 | Fri 6/25/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
634 | Riser #4-2 Replacement, B Living Room 17th-3rd | Test/Insulate | 5 days | Wed 6/23/21 | Tue 6/29/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
635 | Riser #4-2 Replacement, B Living Room 17th-3rd | Restore Service | 1 day | Mon 6/28/21 | Mon 6/28/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
636 | Riser #4-2 Replacement, B Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Wed 6/23/21 | Wed 6/30/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
637 | Riser #4-2 Replacement, B Living Room 17th-3rd | Substantial Completion | 1 day | Thu 7/1/21 | Thu 7/1/21 | 17A, 17B, 16A, 16B, 15A, 15B, 14A, 14B, 13A, 13B, 12A, 12B, 11A, 11B, 10A, 10B, 9A, 9B, 8A, 8B, 7A, 7B, 6A, 6B, 5A, 5B, 4A, 4B |
638 | Riser #3-3 Replacement, A Living Room 41st-18th | 12 days | Fri 6/25/21 | Tue 7/13/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, | |
639 | Riser #3-3 Replacement, A Living Room 41st-18th | Drywall Abatement | 8 days | Fri 6/25/21 | Wed 7/7/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
640 | Riser #3-3 Replacement, A Living Room 41st-18th | Demolish old piping-Riser Outage | 8 days | Mon 6/28/21 | Thu 7/8/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
641 | Riser #3-3 Replacement, A Living Room 41st-18th | Install New Piping | 8 days | Mon 6/28/21 | Thu 7/8/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
642 | Riser #3-3 Replacement, A Living Room 41st-18th | Test/Insulate | 8 days | Tue 6/29/21 | Fri 7/9/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
643 | Riser #3-3 Replacement, A Living Room 41st-18th | Restore Service | 1 day | Fri 7/9/21 | Fri 7/9/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
644 | Riser #3-3 Replacement, A Living Room 41st-18th | Drywall Repair/Paint | 9 days | Tue 6/29/21 | Mon 7/12/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
645 | Riser #3-3 Replacement, A Living Room 41st-18th | Substantial Completion | 1 day | Tue 7/13/21 | Tue 7/13/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
646 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | 12 days | Thu 7/8/21 | Fri 7/23/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, | |
647 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Drywall Abatement | 8 days | Thu 7/8/21 | Mon 7/19/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
648 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Demolish old piping-Riser Outage | 8 days | Fri 7/9/21 | Tue 7/20/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
649 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Install New Piping | 8 days | Fri 7/9/21 | Tue 7/20/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
650 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Test/Insulate | 8 days | Mon 7/12/21 | Wed 7/21/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
651 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Restore Service | 1 day | Wed 7/21/21 | Wed 7/21/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
652 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Drywall Repair/Paint | 9 days | Mon 7/12/21 | Thu 7/22/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
653 | Riser #3-4 Replacement, A/B Bathrooms 41st-18th | Substantial Completion | 1 day | Fri 7/23/21 | Fri 7/23/21 | 42A, 41A, 40A, 39A, 38A, 37A, 36A, 35A, 34A, 33A, 32A, 31A, 30A, 29A, 28A, 27A, 26A, 25A, 24A, 23A, 22A, 21A, 20A, 19A, 18A, |
654 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | 12 days | Tue 7/20/21 | Wed 8/4/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, | |
655 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Drywall Abatement | 8 days | Tue 7/20/21 | Thu 7/29/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
656 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Demolish old piping-Riser Outage | 8 days | Wed 7/21/21 | Fri 7/30/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
657 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Install New Piping | 8 days | Wed 7/21/21 | Fri 7/30/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
658 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Test/Insulate | 8 days | Thu 7/22/21 | Mon 8/2/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
659 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Restore Service | 1 day | Mon 8/2/21 | Mon 8/2/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
660 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Drywall Repair/Paint | 9 days | Thu 7/22/21 | Tue 8/3/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
661 | Riser #3-5 Replacement, N/M Bathrooms 41st-18th | Substantial Completion | 1 day | Wed 8/4/21 | Wed 8/4/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34N, 33N, 32N, 31N, 30N, 29N, 28N, 27N, 26N, 25N, 24N, 23N, 22N, 21N, 20N, 19N, 18N, |
662 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | 9 days | Fri 7/30/21 | Wed 8/11/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A | |
663 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Drywall Abatement | 4 days | Fri 7/30/21 | Wed 8/4/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
664 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Demolish old piping-Riser Outage | 4 days | Mon 8/2/21 | Thu 8/5/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
665 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Install New Piping | 4 days | Mon 8/2/21 | Thu 8/5/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
666 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Test/Insulate | 5 days | Tue 8/3/21 | Mon 8/9/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
667 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Restore Service | 1 day | Fri 8/6/21 | Fri 8/6/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
668 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Drywall Repair/Paint | 6 days | Tue 8/3/21 | Tue 8/10/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
669 | Riser #4-5 Replacement, N/M Bathrooms 17th-3rd | Substantial Completion | 1 day | Wed 8/11/21 | Wed 8/11/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
670 | Riser #3-6 Replacement, M Living Room 41st-18th | 12 days | Thu 8/5/21 | Fri 8/20/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, | |
671 | Riser #3-6 Replacement, M Living Room 41st-18th | Drywall Abatement | 8 days | Thu 8/5/21 | Mon 8/16/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
672 | Riser #3-6 Replacement, M Living Room 41st-18th | Demolish old piping-Riser Outage | 8 days | Fri 8/6/21 | Tue 8/17/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
673 | Riser #3-6 Replacement, M Living Room 41st-18th | Install New Piping | 8 days | Fri 8/6/21 | Tue 8/17/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
674 | Riser #3-6 Replacement, M Living Room 41st-18th | Test/Insulate | 8 days | Mon 8/9/21 | Wed 8/18/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
675 | Riser #3-6 Replacement, M Living Room 41st-18th | Restore Service | 1 day | Wed 8/18/21 | Wed 8/18/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
676 | Riser #3-6 Replacement, M Living Room 41st-18th | Drywall Repair/Paint | 9 days | Mon 8/9/21 | Thu 8/19/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
677 | Riser #3-6 Replacement, M Living Room 41st-18th | Substantial Completion | 1 day | Fri 8/20/21 | Fri 8/20/21 | 42D, 41N, 40N, 39N, 38N, 37N, 36N, 35N, 34M, 33M, 32M, 31M, 30M, 29M, 28M, 27M, 26M, 25M, 24M, 23M, 22M, 21M, 20M, 19M, 18M, |
678 | Riser #4-7 Replacement, M Living Room 17th-3rd | 9 days | Tue 8/17/21 | Fri 8/27/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G | |
679 | Riser #4-7 Replacement, M Living Room 17th-3rd | Drywall Abatement | 4 days | Tue 8/17/21 | Fri 8/20/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
680 | Riser #4-7 Replacement, M Living Room 17th-3rd | Demolish old piping-Riser Outage | 4 days | Wed 8/18/21 | Mon 8/23/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
681 | Riser #4-7 Replacement, M Living Room 17th-3rd | Install New Piping | 4 days | Wed 8/18/21 | Mon 8/23/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
682 | Riser #4-7 Replacement, M Living Room 17th-3rd | Test/Insulate | 5 days | Thu 8/19/21 | Wed 8/25/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
683 | Riser #4-7 Replacement, M Living Room 17th-3rd | Restore Service | 1 day | Tue 8/24/21 | Tue 8/24/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
684 | Riser #4-7 Replacement, M Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Thu 8/19/21 | Thu 8/26/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
685 | Riser #4-7 Replacement, M Living Room 17th-3rd | Substantial Completion | 1 day | Fri 8/27/21 | Fri 8/27/21 | 17M, 16M, 15M, 14M, 13M, 12M, 11M, 10M, 9M, 8M, 7M, 6M, 5M, 4M, 3G |
686 | Riser #3-7 Replacement, L Living Room 41st-18th | 12 days | Mon 8/23/21 | Wed 9/8/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L | |
687 | Riser #3-7 Replacement, L Living Room 41st-18th | Drywall Abatement | 8 days | Mon 8/23/21 | Wed 9/1/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
688 | Riser #3-7 Replacement, L Living Room 41st-18th | Demolish old piping-Riser Outage | 8 days | Tue 8/24/21 | Thu 9/2/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
689 | Riser #3-7 Replacement, L Living Room 41st-18th | Install New Piping | 8 days | Tue 8/24/21 | Thu 9/2/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
690 | Riser #3-7 Replacement, L Living Room 41st-18th | Test/Insulate | 8 days | Wed 8/25/21 | Fri 9/3/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
691 | Riser #3-7 Replacement, L Living Room 41st-18th | Restore Service | 1 day | Fri 9/3/21 | Fri 9/3/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
692 | Riser #3-7 Replacement, L Living Room 41st-18th | Drywall Repair/Paint | 9 days | Wed 8/25/21 | Tue 9/7/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
693 | Riser #3-7 Replacement, L Living Room 41st-18th | Substantial Completion | 1 day | Wed 9/8/21 | Wed 9/8/21 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
694 | Riser #4-8 Replacement, L Living Room 17th-3rd | 9 days | Thu 9/2/21 | Wed 9/15/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F | |
695 | Riser #4-8 Replacement, L Living Room 17th-3rd | Drywall Abatement | 4 days | Thu 9/2/21 | Wed 9/8/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
696 | Riser #4-8 Replacement, L Living Room 17th-3rd | Demolish old piping-Riser Outage | 4 days | Fri 9/3/21 | Thu 9/9/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
697 | Riser #4-8 Replacement, L Living Room 17th-3rd | Install New Piping | 4 days | Fri 9/3/21 | Thu 9/9/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
698 | Riser #4-8 Replacement, L Living Room 17th-3rd | Test/Insulate | 5 days | Tue 9/7/21 | Mon 9/13/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
699 | Riser #4-8 Replacement, L Living Room 17th-3rd | Restore Service | 1 day | Fri 9/10/21 | Fri 9/10/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
700 | Riser #4-8 Replacement, L Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Tue 9/7/21 | Tue 9/14/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
701 | Riser #4-8 Replacement, L Living Room 17th-3rd | Substantial Completion | 1 day | Wed 9/15/21 | Wed 9/15/21 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
702 | Riser #5-3 Replacement, K Living Room 41st-18th | 12 days | Thu 9/9/21 | Fri 9/24/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L | |
703 | Riser #5-3 Replacement, K Living Room 41st-18th | Drywall Abatement | 8 days | Thu 9/9/21 | Mon 9/20/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
704 | Riser #5-3 Replacement, K Living Room 41st-18th | Demolish old piping-Riser Outage | 8 days | Fri 9/10/21 | Tue 9/21/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
705 | Riser #5-3 Replacement, K Living Room 41st-18th | Install New Piping | 8 days | Fri 9/10/21 | Tue 9/21/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
706 | Riser #5-3 Replacement, K Living Room 41st-18th | Test/Insulate | 8 days | Mon 9/13/21 | Wed 9/22/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
707 | Riser #5-3 Replacement, K Living Room 41st-18th | Restore Service | 1 day | Wed 9/22/21 | Wed 9/22/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
708 | Riser #5-3 Replacement, K Living Room 41st-18th | Drywall Repair/Paint | 9 days | Mon 9/13/21 | Thu 9/23/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
709 | Riser #5-3 Replacement, K Living Room 41st-18th | Substantial Completion | 1 day | Fri 9/24/21 | Fri 9/24/21 | 42D, 41K, 41L, 40K, 40L, 39K, 39L, 38K, 38L, 37K, 37L, 36K, 36L, 35K, 35L, 34KA, 34L, 33K, 33L, 32K, 32L, 31J, 31L, 30K, 30L, 29K, 29L, 28K, 28L, 27K, 27L, 26K, 26L, 25K, 25L, 24K, 24L, 23K, 23L, 22K, 22L, 21K, 21L, 20K, 20L, 19K, 19L, 18K, 18L |
710 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | 10 days | Tue 9/21/21 | Mon 10/4/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E | |
711 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Drywall Abatement | 5 days | Tue 9/21/21 | Mon 9/27/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
712 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Demolish old piping-Riser Outage | 5 days | Thu 9/23/21 | Wed 9/29/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
713 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Install New Piping | 5 days | Thu 9/23/21 | Wed 9/29/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
714 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Test/Insulate | 5 days | Fri 9/24/21 | Thu 9/30/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
715 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Restore Service | 1 day | Thu 9/30/21 | Thu 9/30/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
716 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Drywall Repair/Paint | 6 days | Fri 9/24/21 | Fri 10/1/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
717 | Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3] | Substantial Completion | 1 day | Mon 10/4/21 | Mon 10/4/21 | 42D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K, 33K, 32K, 31K, 30K, 29K, 28K, 27K, 26K, 25K, 24K, 23K, 22K, 21K, 20K, 19K, 18K, 17K, 16K, 15K, 14K, 13K, 12K, 11K, 10K, 9K, 8K, 7K, 6K, 5K, 4K, 3E |
718 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | 9 days | Tue 9/28/21 | Fri 10/8/21 | ELEVATOR HALLWAYS | |
719 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Drywall Abatement | 5 days | Tue 9/28/21 | Mon 10/4/21 | ELEVATOR HALLWAYS |
720 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Demolish old piping-Riser Outage | 5 days | Wed 9/29/21 | Tue 10/5/21 | ELEVATOR HALLWAYS |
721 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Install New Piping | 5 days | Wed 9/29/21 | Tue 10/5/21 | ELEVATOR HALLWAYS |
722 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Test/Insulate | 5 days | Thu 9/30/21 | Wed 10/6/21 | ELEVATOR HALLWAYS |
723 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Restore Service | 1 day | Wed 10/6/21 | Wed 10/6/21 | ELEVATOR HALLWAYS |
724 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Drywall Repair/Paint | 6 days | Thu 9/30/21 | Thu 10/7/21 | ELEVATOR HALLWAYS |
725 | Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3] | Substantial Completion | 1 day | Fri 10/8/21 | Fri 10/8/21 | ELEVATOR HALLWAYS |
726 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | 17 days | Tue 10/5/21 | Wed 10/27/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G | |
727 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Drywall Abatement | 13 days | Tue 10/5/21 | Thu 10/21/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
728 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Demolish old piping-Riser Outage | 13 days | Wed 10/6/21 | Fri 10/22/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
729 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Install New Piping | 13 days | Wed 10/6/21 | Fri 10/22/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
730 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Test/Insulate | 13 days | Thu 10/7/21 | Mon 10/25/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
731 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Restore Service | 1 day | Mon 10/25/21 | Mon 10/25/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
732 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Drywall Repair/Paint | 14 days | Thu 10/7/21 | Tue 10/26/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
733 | Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER] | Substantial Completion | 1 day | Wed 10/27/21 | Wed 10/27/21 | 42B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G, 37F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G, 32F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G, 27F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G, 22F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G, 17F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G, 12F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G, 7F, 7G, 6F, 6G, 5F, 5G, 4F, 4G |
734 | Riser #6-3 Replacement, K Living Room 17th-3rd | 9 days | Fri 10/22/21 | Wed 11/3/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F | |
735 | Riser #6-3 Replacement, K Living Room 17th-3rd | Drywall Abatement | 5 days | Fri 10/22/21 | Thu 10/28/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
736 | Riser #6-3 Replacement, K Living Room 17th-3rd | Demolish old piping-Riser Outage | 5 days | Mon 10/25/21 | Fri 10/29/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
737 | Riser #6-3 Replacement, K Living Room 17th-3rd | Install New Piping | 5 days | Mon 10/25/21 | Fri 10/29/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
738 | Riser #6-3 Replacement, K Living Room 17th-3rd | Test/Insulate | 5 days | Tue 10/26/21 | Mon 11/1/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
739 | Riser #6-3 Replacement, K Living Room 17th-3rd | Restore Service | 1 day | Mon 11/1/21 | Mon 11/1/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
740 | Riser #6-3 Replacement, K Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Tue 10/26/21 | Tue 11/2/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
741 | Riser #6-3 Replacement, K Living Room 17th-3rd | Substantial Completion | 1 day | Wed 11/3/21 | Wed 11/3/21 | 17K, 17L, 16K, 16L, 15K, 15L, 14K, 14L, 13K, 13L, 12K, 12L, 11K, 11L, 10K, 10LB, 9K, 9L, 8K, 8L, 7K, 7L, 6K, 6L, 5K, 5L, 4K, 4L, 3E, 3F |
742 | Riser #1-4 Replacement, D Bedroom 41st-3rd | 17 days | Fri 10/29/21 | Mon 11/22/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D | |
743 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Drywall Abatement | 13 days | Fri 10/29/21 | Tue 11/16/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
744 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Demolish old piping-Riser Outage | 13 days | Mon 11/1/21 | Wed 11/17/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
745 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Install New Piping | 13 days | Mon 11/1/21 | Wed 11/17/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
746 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Test/Insulate | 13 days | Tue 11/2/21 | Thu 11/18/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
747 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Restore Service | 1 day | Thu 11/18/21 | Thu 11/18/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
748 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Drywall Repair/Paint | 14 days | Tue 11/2/21 | Fri 11/19/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
749 | Riser #1-4 Replacement, D Bedroom 41st-3rd | Substantial Completion | 1 day | Mon 11/22/21 | Mon 11/22/21 | 42A, 41C, 41D, 40C, 40D, 39C, 39D, 38C, 38D, 37C, 37D, 36C, 36D, 35C, 35D, 34C, 34D, 33C, 33D, 32C, 32D, 31C, 31D, 30C, 30D, 29C, 29D, 28C, 28D, 27C, 27D, 26C, 26D, 25C, 25D, 24C, 24D, 23C, 23D, 22C, 22D, 21C, 21D, 20C, 20D, 19C, 19D, 18C, 18D, 17C, 17D, 16C, 16D, 15C, 15D, 14C, 14D, 13C, 13D, 12C, 12D, 11C, 11D, 10C, 10D, 9C, 9D, 8C, 8D, 7C, 7D, 6C, 6D, 5C, 5D, 4C, 4D |
750 | Riser #4-6 Replacement, N Living Room 17th-3rd | 9 days | Wed 11/17/21 | Wed 12/1/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A | |
751 | Riser #4-6 Replacement, N Living Room 17th-3rd | Drywall Abatement | 5 days | Wed 11/17/21 | Tue 11/23/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
752 | Riser #4-6 Replacement, N Living Room 17th-3rd | Demolish old piping-Riser Outage | 5 days | Thu 11/18/21 | Wed 11/24/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
753 | Riser #4-6 Replacement, N Living Room 17th-3rd | Install New Piping | 5 days | Thu 11/18/21 | Wed 11/24/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
754 | Riser #4-6 Replacement, N Living Room 17th-3rd | Test/Insulate | 5 days | Fri 11/19/21 | Mon 11/29/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
755 | Riser #4-6 Replacement, N Living Room 17th-3rd | Restore Service | 1 day | Mon 11/29/21 | Mon 11/29/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
756 | Riser #4-6 Replacement, N Living Room 17th-3rd | Drywall Repair/Paint | 6 days | Fri 11/19/21 | Tue 11/30/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
757 | Riser #4-6 Replacement, N Living Room 17th-3rd | Substantial Completion | 1 day | Wed 12/1/21 | Wed 12/1/21 | 17N, 16N, 15N, 14N, 13N, 12N, 11N, 10N, 9N, 8N, 7N, 6N, 5N, 4N, 3A |
758 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | 17 days | Wed 11/24/21 | Mon 12/20/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E | |
759 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Drywall Abatement | 13 days | Wed 11/24/21 | Tue 12/14/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
760 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Demolish old piping-Riser Outage | 13 days | Mon 11/29/21 | Wed 12/15/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
761 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Install New Piping | 13 days | Mon 11/29/21 | Wed 12/15/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
762 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Test/Insulate | 13 days | Tue 11/30/21 | Thu 12/16/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
763 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Restore Service | 1 day | Thu 12/16/21 | Thu 12/16/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
764 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Drywall Repair/Paint | 14 days | Tue 11/30/21 | Fri 12/17/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
765 | Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Substantial Completion | 1 day | Mon 12/20/21 | Mon 12/20/21 | 42B, 41E, 40E, 39E, 38E, 37E, 36E, 35E, 34E, 33E, 32E, 31E, 30E, 29E, 28E, 27E, 26E, 25E, 24E, 23E, 22E, 21E, 20E, 19E, 18E, 17E, 16E, 15E, 14E, 13E, 12E, 11E, 10E, 9E, 8E, 7E, 6E, 5E, 4E |
766 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | 17 days | Wed 12/15/21 | Mon 1/10/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C | |
767 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Drywall Abatement | 13 days | Wed 12/15/21 | Tue 1/4/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
768 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Demolish old piping-Riser Outage | 13 days | Thu 12/16/21 | Wed 1/5/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
769 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Install New Piping | 13 days | Thu 12/16/21 | Wed 1/5/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
770 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Test/Insulate | 13 days | Fri 12/17/21 | Thu 1/6/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
771 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Restore Service | 1 day | Thu 1/6/22 | Thu 1/6/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
772 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Drywall Repair/Paint | 14 days | Fri 12/17/21 | Fri 1/7/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
773 | Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT] | Substantial Completion | 1 day | Mon 1/10/22 | Mon 1/10/22 | 42A, 41C, 40C, 39C, 38C, 37C, 36C, 35C, 34C, 33C, 32C, 31C, 30C, 29C, 28C, 27C, 26C, 25C, 24C, 23C, 22C, 21C, 20C, 19C, 18C, 17, 16C, 15C, 14C, 13C, 12C, 11C, 10C, 9C, 8C, 7C, 6C, 5C, 4C |
774 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | 13 days | Wed 1/5/22 | Fri 1/21/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J | |
775 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Drywall Abatement | 7 days | Wed 1/5/22 | Thu 1/13/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
776 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Demolish old piping-Riser Outage | 7 days | Thu 1/6/22 | Fri 1/14/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
777 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Install New Piping | 7 days | Thu 1/6/22 | Fri 1/14/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
778 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Test/Insulate | 7 days | Fri 1/7/22 | Mon 1/17/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
779 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Restore Service | 1 day | Mon 1/17/22 | Mon 1/17/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
780 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Drywall Repair/Paint | 10 days | Fri 1/7/22 | Thu 1/20/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
781 | Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Substantial Completion | 1 day | Fri 1/21/22 | Fri 1/21/22 | 42C, 41J, 40J, 39J, 38J, 37J, 36J, 35J, 34J, 33J, 32J, 31J, 30J, 29J, 28J, 27J, 26J, 25J, 24J, 23J, 22J, 21J, 20J, 19J, 18J |
782 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | 10 days | Fri 1/14/22 | Thu 1/27/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D | |
783 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Drywall Abatement | 4 days | Fri 1/14/22 | Wed 1/19/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
784 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Demolish old piping-Riser Outage | 4 days | Mon 1/17/22 | Thu 1/20/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
785 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Install New Piping | 4 days | Mon 1/17/22 | Thu 1/20/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
786 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Test/Insulate | 4 days | Tue 1/18/22 | Fri 1/21/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
787 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Restore Service | 1 day | Fri 1/21/22 | Fri 1/21/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
788 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Drywall Repair/Paint | 7 days | Tue 1/18/22 | Wed 1/26/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
789 | Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Substantial Completion | 1 day | Thu 1/27/22 | Thu 1/27/22 | 17J, 16J, 15J, 14J, 13J, 12J, 11J, 10J, 9J, 8J, 7J, 6J, 5J, 4J, 3D |
790 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | 13 days | Thu 1/20/22 | Mon 2/7/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L | |
791 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Drywall Abatement | 7 days | Thu 1/20/22 | Fri 1/28/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
792 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Demolish old piping-Riser Outage | 7 days | Fri 1/21/22 | Mon 1/31/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
793 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Install New Piping | 7 days | Fri 1/21/22 | Mon 1/31/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
794 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Test/Insulate | 7 days | Mon 1/24/22 | Tue 2/1/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
795 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Restore Service | 1 day | Tue 2/1/22 | Tue 2/1/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
796 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Drywall Repair/Paint | 10 days | Mon 1/24/22 | Fri 2/4/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
797 | Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT] | Substantial Completion | 1 day | Mon 2/7/22 | Mon 2/7/22 | 42D, 41L, 40L, 39L, 38L, 37L, 36L, 35L, 34L, 33L, 32L, 31L, 30L, 29L, 28L, 27L, 26L, 25L, 24L, 23L, 22L, 21L, 20L, 19L, 18L |
798 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | 10 days | Mon 1/31/22 | Fri 2/11/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F | |
799 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Drywall Abatement | 4 days | Mon 1/31/22 | Thu 2/3/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
800 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Demolish old piping-Riser Outage | 4 days | Tue 2/1/22 | Fri 2/4/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
801 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Install New Piping | 4 days | Tue 2/1/22 | Fri 2/4/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
802 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Test/Insulate | 4 days | Wed 2/2/22 | Mon 2/7/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
803 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Restore Service | 1 day | Mon 2/7/22 | Mon 2/7/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
804 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Drywall Repair/Paint | 7 days | Wed 2/2/22 | Thu 2/10/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |
805 | Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT] | Substantial Completion | 1 day | Fri 2/11/22 | Fri 2/11/22 | 17L, 16L, 15L, 14L, 13L, 12L, 11L, 10L, 9L, 8L, 7L, 6L, 5L, 4L, 3F |