O
Task Name
Duration
Start
Finish
Affected Units
2Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]
3Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/11/219/2/2142B, 41E, 40E, 39E, 38E
4Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/12/219/3/2137E, 36E, 35E, 34E, 33E
5Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/13/219/7/2132E, 31E, 30E, 29E, 28E
6Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/16/219/8/2127E, 26E, 25E, 24E, 23E
7Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/17/219/9/2122E, 21E, 20E, 19E, 18E
8Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/18/219/10/2117E, 16E, 15E, 14E, 13E
9Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/19/219/13/2112E, 11E, 10E, 9E, 8E
10Riser #1-1 Replacement, E Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/20/219/14/217E, 6E, 5E, 4E
11Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]
12Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/23/219/15/2142A, 41C, 40C, 39C, 38C
13Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/24/219/16/2137C, 36C, 35C, 34C, 33C
14Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/25/219/17/2132C, 31C, 30C, 29C, 28C
15Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/26/219/20/2127C, 26C, 25C, 24C, 23C
16Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/27/219/21/2122C, 21C, 20C, 19C, 18C
17Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/30/219/22/2117, 16C, 15C, 14C, 13C
18Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days8/31/219/23/2112C, 11C, 10C, 9C, 8C
19Riser #1-5 Replacement, C Hall Bath/Master Bedroom 41st-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins24 Days9/1/219/24/217C, 6C, 5C, 4C
20Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]
21Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Hydronic Pipe replacement begins22 days9/1/219/27/2142D, 41K, 40K, 39K, 38K, 37K, 36K, 35K, 34K
22Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Hydronic Pipe replacement begins22 days9/2/219/28/2133K, 32K, 31K, 30K, 29K, 28K, 27K, 26K
23Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Hydronic Pipe replacement begins22 days9/3/219/29/2125K, 24K, 23K, 22K, 21K, 20K, 19K, 18K
24Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Hydronic Pipe replacement begins22 days9/7/219/30/2117K, 16K, 15K, 14K, 13K, 12K, 11K, 10K
25Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Hydronic Pipe replacement begins22 days9/8/2110/1/219K, 8K, 7K, 6K, 5K, 4K, 3E
26Riser #5-1 Replacement, J Hall Bath/Master Bedroom 41st-18th [NO ADD'L ABATEMENT]
27Riser #5-1 Replacement, J Hall Bath/Master Bedroom 41st-18th [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days9/10/2110/5/2142C, 41J, 40J, 39J, 38J
28Riser #5-1 Replacement, J Hall Bath/Master Bedroom 41st-18th [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days9/13/2110/6/2137J, 36J, 35J, 34J, 33J
29Riser #5-1 Replacement, J Hall Bath/Master Bedroom 41st-18th [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days9/14/2110/7/2132J, 31J, 30J, 29J, 28J
30Riser #5-1 Replacement, J Hall Bath/Master Bedroom 41st-18th [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days9/15/2110/8/2127J, 26J, 25J, 24J, 23J
31Riser #5-1 Replacement, J Hall Bath/Master Bedroom 41st-18th [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days9/16/2110/11/2122J, 21J, 20J, 19J, 18J
32Riser #6-1 Replacement, J Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]
33Riser #6-1 Replacement, J Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins20 days9/16/2110/11/2117J, 16J, 15J, 14J, 13J
34Riser #6-1 Replacement, J Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins20 days9/17/2110/12/2112J, 11J, 10J, 9J, 8J
35Riser #6-1 Replacement, J Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins20 days9/20/2110/13/217J, 6J, 5J, 4J, 3D
3617th Floor Hydronc Ceiling Abatement
3717th Floor Hydronc Ceiling AbatementAbatement Begins8 days9/10/219/15/2117J
3817th Floor Hydronc Ceiling AbatementAbatement Begins8 days9/13/219/16/2117K
3917th Floor Hydronc Ceiling AbatementAbatement Begins8 days9/14/219/17/2117L
4017th Floor Hydronc Ceiling AbatementAbatement Begins8 days9/15/219/20/2117M
4117th Floor Hydronc Ceiling AbatementAbatement Begins8 days9/16/219/21/2117N
42Riser #4-7 Replacement, M Living Room 17th-3rd
43Riser #4-7 Replacement, M Living Room 17th-3rdHydronic Pipe replacement begins20 days9/21/2110/14/2117M, 16M, 15M, 14M, 13M
44Riser #4-7 Replacement, M Living Room 17th-3rdHydronic Pipe replacement begins20 days9/22/2110/15/2112M, 11M, 10M, 9M, 8M
45Riser #4-7 Replacement, M Living Room 17th-3rdHydronic Pipe replacement begins20 days9/23/2110/18/217M, 6M, 5M, 4M, 3G
46Riser #3-6 Replacement, M Living Room 41st-18th
47Riser #3-6 Replacement, M Living Room 41st-18thHydronic Pipe replacement begins26 days9/24/2110/25/2142D, 41M, 40M, 39M, 38M
48Riser #3-6 Replacement, M Living Room 41st-18thHydronic Pipe replacement begins26 days9/27/2110/26/2137M, 36M, 35M, 34M, 33M
49Riser #3-6 Replacement, M Living Room 41st-18thHydronic Pipe replacement begins26 days9/28/2110/27/2132M, 31M, 30M, 29M, 28M
50Riser #3-6 Replacement, M Living Room 41st-18thHydronic Pipe replacement begins26 days9/29/2110/28/2127M, 26M, 25M, 24M, 23M
51Riser #3-6 Replacement, M Living Room 41st-18thHydronic Pipe replacement begins26 days9/30/2110/29/2122M, 21M, 20M, 19M, 18M
52Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]
53Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Hydronic Pipe replacement begins26 days9/24/2110/25/21ELEVATOR HALLWAYS: 42, 41, 40, 39, 38, 37, 36, 35, 34
54Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Hydronic Pipe replacement begins26 days9/27/2110/26/21ELEVATOR HALLWAYS: 33, 32, 31, 30, 29, 28, 27, 26
55Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Hydronic Pipe replacement begins26 days9/28/2110/27/21ELEVATOR HALLWAYS: 25, 24, 23, 22, 21, 20, 19, 18,
56Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Hydronic Pipe replacement begins26 days9/29/2110/28/21ELEVATOR HALLWAYS: 17, 16, 15, 14, 13, 12, 11, 10
57Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Hydronic Pipe replacement begins26 days9/30/2110/29/21ELEVATOR HALLWAYS: 9, 8, 7, 6, 5, 4, 3,
5817th Floor Hydronic Ceiling lateral Pipe Replacement
5917th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days9/27/2110/12/2117J, 17K
6017th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days9/28/2110/13/2117K, 17L
6117th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days9/29/2110/14/2117L, 17M
6217th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days9/30/2110/15/2117M, 17N
6317th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days10/1/2110/18/2117N, 17A
6417th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days10/4/2110/19/2117A, 17B
6517th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days10/5/2110/20/2117B, 17C
6617th Floor Hydronic Ceiling lateral Pipe ReplacementHydronic Pipe replcement begins19 days10/6/2110/21/2117C
67Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]
68Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/1/2110/25/2142B, 41F, 41G, 40F, 40G, 39F, 39G, 38F, 38G
69Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/4/2110/26/2137F, 37G, 36F, 36G, 35F, 35G, 34F, 34G, 33F, 33G
70Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/5/2110/27/2132F, 32G, 31F, 31G, 30F, 30G, 29F, 29G, 28F, 28G
71Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/6/2110/28/2127F, 27G, 26F, 26G, 25F, 25G, 24F, 24G, 23F, 23G
72Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/7/2110/29/2122F, 22G, 21F, 21G, 20F, 20G, 19F, 19G, 18F, 18G
73Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/8/2111/1/2117F, 17G, 16F, 16G, 15F, 15G, 14F, 14G, 13F, 13G
74Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/11/2111/2/2112F, 12G, 11F, 11G, 10F, 10G, 9F, 9G, 8F, 8G
75Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Hydronic Pipe replacement begins24 Days10/12/2111/3/217F, 7G, 6F, 6G, 5F, 5G, 4F, 4G
7617th Floor Hydronic Ceiling Lateral Pipe ReplacementHydronic Lateral Pipe replacemnt begins
7717th Floor Hydronic Ceiling Lateral Pipe Replacement6 Days10/13/2110/18/2117A
7817th Floor Hydronic Ceiling Lateral Pipe Replacement6 Days10/14/2110/19/2117B,
7917th Floor Hydronic Ceiling Lateral Pipe Replacement6 Days10/15/2110/20/2117C
80Riser #5-4 Replacement, L Hall Bath/Master Bedroom 41st - 18thrd [NO ADD'L ABATEMENT]
81Riser #5-4 Replacement, L Hall Bath/Master Bedroom 41st - 18thrd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days10/14/2111/8/2142D, 41L, 40L, 39L, 38L
82Riser #5-4 Replacement, L Hall Bath/Master Bedroom 41st - 18thrd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days10/15/2111/9/2137L, 36L, 35L, 34L, 33L
83Riser #5-4 Replacement, L Hall Bath/Master Bedroom 41st - 18thrd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days10/18/2111/10/2132L, 31L, 30L, 29L, 28L
84Riser #5-4 Replacement, L Hall Bath/Master Bedroom 41st - 18thrd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days10/19/2111/11/2127L, 26L, 25L, 24L, 23L
85Riser #5-4 Replacement, L Hall Bath/Master Bedroom 41st - 18thrd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins22 days10/20/2111/12/2122L, 21L, 20L, 19L, 18L
86Riser #6-4 Replacement, L Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]
87Riser #6-4 Replacement, L Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins20 days10/20/2111/12/2117L, 16L, 15L, 14L, 13L
88Riser #6-4 Replacement, L Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins20 days10/21/2111/15/2112L, 11L, 10L, 9L, 8L
89Riser #6-4 Replacement, L Hall Bath/Master Bedroom 17th-3rd [NO ADD'L ABATEMENT]Hydronic Pipe replacement begins20 days10/22/2111/16/216L, 5L, 4L, 3F
9042nd Floor Hydronic & Remaining Domestic Lateral Pipe Replacement
9142nd Floor Hydronic & Remaining Domestic Lateral Pipe ReplacementHydronic Lateral Pipe replacemnt begins36 Days4/4/215/14/2142A
9242nd Floor Hydronic & Remaining Domestic Lateral Pipe ReplacementHydronic Lateral Pipe replacemnt begins36 Days4/5/215/17/2142B
9342nd Floor Hydronic & Remaining Domestic Lateral Pipe ReplacementHydronic Lateral Pipe replacemnt begins36 Days4/6/215/18/2142C
9442nd Floor Hydronic & Remaining Domestic Lateral Pipe ReplacementHydronic Lateral Pipe replacemnt begins36 Days4/7/215/19/2142D
951st/2nd/Garage main DWV-DomesticMains drain work begins62 Days1/3/213/29/212nd Floor, lobby, sub basement