3PH 42A/B Final Pass DWV & Domestic & HVAC Replacement34 daysMon 8/3/20Fri 9/18/20
4PH 42A/B Final Pass DWV & Domestic & HVAC ReplacementDemoltion & Abatement2 daysMon 8/3/20Tue 8/4/20
5PH 42A/B Final Pass DWV & Domestic & HVAC ReplacementPlumbing Replacement & Inspections5 daysWed 8/5/20Tue 8/11/20
6PH 42A/B Final Pass DWV & Domestic & HVAC ReplacementDrywall Repair & Inspections9 daysWed 8/12/20Mon 8/24/20
7PH 42A/B Final Pass DWV & Domestic & HVAC ReplacementTexture/Paint6 daysTue 8/25/20Tue 9/1/20
8PH 42A/B Final Pass DWV & Domestic & HVAC ReplacementTile, Carpentry & Reconstruction10 daysWed 9/2/20Wed 9/16/20
9PH 42A/B Final Pass DWV & Domestic & HVAC ReplacementSubstantial Completion & Punchlist2 daysThu 9/17/20Fri 9/18/20
1041C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-334 daysMon 8/3/20Fri 9/18/20
1141C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysMon 8/3/20Tue 8/4/20
1241C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections5 daysTue 8/4/20Mon 8/10/20
1341C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections8 daysTue 8/11/20Thu 8/20/20
1441C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3Texture/Paint6 daysFri 8/21/20Fri 8/28/20
1541C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction12 daysMon 8/31/20Wed 9/16/20
1641C 3rd Bathroom & 41E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysThu 9/17/20Fri 9/18/20
1740C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-334 daysMon 8/10/20Fri 9/25/20
1840C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysMon 8/10/20Tue 8/11/20
1940C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 8/11/20Thu 8/13/20
2040C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections9 daysFri 8/14/20Wed 8/26/20
2140C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3Texture/Paint6 daysThu 8/27/20Thu 9/3/20
2240C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction13 daysFri 9/4/20Wed 9/23/20
2340C 3rd Bathroom & 40E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysThu 9/24/20Fri 9/25/20
2439C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-334 daysTue 8/11/20Mon 9/28/20
2539C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysTue 8/11/20Wed 8/12/20
2639C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 8/12/20Fri 8/14/20
2739C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections8 daysMon 8/17/20Wed 8/26/20
2839C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3Texture/Paint5 daysThu 8/27/20Wed 9/2/20
2939C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 9/3/20Thu 9/24/20
3039C 3rd Bathroom & 39E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysFri 9/25/20Mon 9/28/20
3138C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-334 daysWed 8/12/20Tue 9/29/20
3238C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysWed 8/12/20Thu 8/13/20
3338C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 8/13/20Mon 8/17/20
3438C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections8 daysTue 8/18/20Thu 8/27/20
3538C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3Texture/Paint5 daysFri 8/28/20Thu 9/3/20
3638C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysFri 9/4/20Fri 9/25/20
3738C 3rd Bathroom & 38E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysMon 9/28/20Tue 9/29/20
3837C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-334 daysThu 8/13/20Wed 9/30/20
3937C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysThu 8/13/20Fri 8/14/20
4037C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 8/14/20Tue 8/18/20
4137C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections8 daysWed 8/19/20Fri 8/28/20
4237C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3Texture/Paint5 daysMon 8/31/20Fri 9/4/20
4337C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 9/8/20Mon 9/28/20
4437C 3rd Bathroom & 37E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysTue 9/29/20Wed 9/30/20
4536C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-334 daysFri 8/14/20Thu 10/1/20
4636C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysFri 8/14/20Mon 8/17/20
4736C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 8/17/20Wed 8/19/20
4836C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections8 daysThu 8/20/20Mon 8/31/20
4936C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3Texture/Paint5 daysTue 9/1/20Tue 9/8/20
5036C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 9/9/20Tue 9/29/20
5136C 3rd Bathroom & 36E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysWed 9/30/20Thu 10/1/20
5235C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-334 daysMon 8/17/20Fri 10/2/20
5335C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3Demoltion & Abatement2 daysMon 8/17/20Tue 8/18/20
5435C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 8/18/20Thu 8/20/20
5535C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3Drywall Repair & Inspections8 daysFri 8/21/20Tue 9/1/20
5635C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3Texture/Paint5 daysWed 9/2/20Wed 9/9/20
5735C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 9/10/20Wed 9/30/20
5835C 3rd Bathroom & 35E 3rd Bathroom & HVAC R#1-3Substantial Completion & Punchlist2 daysThu 10/1/20Fri 10/2/20
5934D Bathroom & 34D/E Kitchen & HVAC R#1-334 daysTue 8/18/20Mon 10/5/20
6034D Bathroom & 34D/E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysTue 8/18/20Wed 8/19/20
6134D Bathroom & 34D/E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 8/19/20Fri 8/21/20
6234D Bathroom & 34D/E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysMon 8/24/20Wed 9/2/20
6334D Bathroom & 34D/E Kitchen & HVAC R#1-3Texture/Paint5 daysThu 9/3/20Thu 9/10/20
6434D Bathroom & 34D/E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysFri 9/11/20Thu 10/1/20
6534D Bathroom & 34D/E Kitchen & HVAC R#1-3Substantial Completion & Punchlist2 daysFri 10/2/20Mon 10/5/20
6633D Bathroom & 33D/33E Kitchen & HVAC R#1-334 daysWed 8/19/20Tue 10/6/20
6733D Bathroom & 33D/33E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysWed 8/19/20Thu 8/20/20
6833D Bathroom & 33D/33E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 8/20/20Mon 8/24/20
6933D Bathroom & 33D/33E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysTue 8/25/20Thu 9/3/20
7033D Bathroom & 33D/33E Kitchen & HVAC R#1-3Texture/Paint5 daysFri 9/4/20Fri 9/11/20
7133D Bathroom & 33D/33E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 9/14/20Fri 10/2/20
7233D Bathroom & 33D/33E Kitchen & HVAC R#1-3Substantial Completion & Punchlist2 daysMon 10/5/20Tue 10/6/20
7332D Bathroom & 32D/33E Kitchen & HVAC R#1-334 daysThu 8/20/20Wed 10/7/20
7432D Bathroom & 32D/33E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 8/20/20Fri 8/21/20
7532D Bathroom & 32D/33E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 8/21/20Tue 8/25/20
7632D Bathroom & 32D/33E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 8/26/20Fri 9/4/20
7732D Bathroom & 32D/33E Kitchen & HVAC R#1-3Texture/Paint5 daysTue 9/8/20Mon 9/14/20
7832D Bathroom & 32D/33E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 9/15/20Mon 10/5/20
7932D Bathroom & 32D/33E Kitchen & HVAC R#1-3Substantial Completion & Punchlist2 daysTue 10/6/20Wed 10/7/20
80CDE Work Pause for Recovery Schedule15 daysWed 9/2/20Wed 9/23/20
81Riser Valve Installation [SHOULDER]13 daysWed 9/9/20Fri 9/25/20
82Riser Valve Installation [SHOULDER]Demo / Abatement3 daysWed 9/9/20Fri 9/11/20
83Riser Valve Installation [SHOULDER]Plumbing Valve Repalcmet10 daysMon 9/14/20Fri 9/25/20
84Riser Valve Installation [SHOULDER]Temp Access Coverings0 daysFri 9/25/20Fri 9/25/20
8531D Bathroom & 31D/31E Kitchen & HVAC R#1-344 daysWed 9/23/20Mon 11/23/20
8631D Bathroom & 31D/31E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysWed 9/23/20Thu 9/24/20
8731D Bathroom & 31D/31E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 9/24/20Mon 9/28/20
8831D Bathroom & 31D/31E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysTue 9/29/20Thu 10/8/20
8931D Bathroom & 31D/31E Kitchen & HVAC R#1-3Texture/Paint5 daysFri 10/9/20Thu 10/15/20
9031D Bathroom & 31D/31E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysFri 10/16/20Thu 11/5/20
9131D Bathroom & 31D/31E Kitchen & HVAC R#1-3Substantial Completion & Punchlist12 daysFri 11/6/20Mon 11/23/20
9230D Bathroom & 30D/30E Kitchen & HVAC R#1-344 daysThu 9/24/20Tue 11/24/20
9330D Bathroom & 30D/30E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 9/24/20Fri 9/25/20
9430D Bathroom & 30D/30E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 9/25/20Tue 9/29/20
9530D Bathroom & 30D/30E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 9/30/20Fri 10/9/20
9630D Bathroom & 30D/30E Kitchen & HVAC R#1-3Texture/Paint5 daysMon 10/12/20Fri 10/16/20
9730D Bathroom & 30D/30E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 10/19/20Fri 11/6/20
9830D Bathroom & 30D/30E Kitchen & HVAC R#1-3Substantial Completion & Punchlist12 daysMon 11/9/20Tue 11/24/20
9929D Bathroom & 29D/29E Kitchen & HVAC R#1-344 daysFri 9/25/20Wed 11/25/20
10029D Bathroom & 29D/29E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysFri 9/25/20Mon 9/28/20
10129D Bathroom & 29D/29E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 9/28/20Wed 9/30/20
10229D Bathroom & 29D/29E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysThu 10/1/20Mon 10/12/20
10329D Bathroom & 29D/29E Kitchen & HVAC R#1-3Texture/Paint5 daysTue 10/13/20Mon 10/19/20
10429D Bathroom & 29D/29E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 10/20/20Mon 11/9/20
10529D Bathroom & 29D/29E Kitchen & HVAC R#1-3Substantial Completion & Punchlist12 daysTue 11/10/20Wed 11/25/20
10628D Bathroom & 28D/28E Kitchen & HVAC R#1-344 daysMon 9/28/20Mon 11/30/20
10728D Bathroom & 28D/28E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysMon 9/28/20Tue 9/29/20
10828D Bathroom & 28D/28E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 9/29/20Thu 10/1/20
10928D Bathroom & 28D/28E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysFri 10/2/20Tue 10/13/20
11028D Bathroom & 28D/28E Kitchen & HVAC R#1-3Texture/Paint5 daysWed 10/14/20Tue 10/20/20
11128D Bathroom & 28D/28E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 10/21/20Tue 11/10/20
11228D Bathroom & 28D/28E Kitchen & HVAC R#1-3Substantial Completion & Punchlist12 daysWed 11/11/20Mon 11/30/20
11327D Bathroom & 27D/27E Kitchen & HVAC R#1-344 daysTue 9/29/20Tue 12/1/20
11427D Bathroom & 27D/27E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysTue 9/29/20Wed 9/30/20
11527D Bathroom & 27D/27E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 9/30/20Fri 10/2/20
11627D Bathroom & 27D/27E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysMon 10/5/20Wed 10/14/20
11727D Bathroom & 27D/27E Kitchen & HVAC R#1-3Texture/Paint5 daysThu 10/15/20Wed 10/21/20
11827D Bathroom & 27D/27E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 10/22/20Wed 11/11/20
11927D Bathroom & 27D/27E Kitchen & HVAC R#1-3Substantial Completion & Punchlist12 daysThu 11/12/20Tue 12/1/20
12026D Bathroom & 26D/26E Kitchen & HVAC R#1-335 daysWed 9/30/20Tue 11/17/20
12126D Bathroom & 26D/26E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysWed 9/30/20Thu 10/1/20
12226D Bathroom & 26D/26E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 10/1/20Mon 10/5/20
12326D Bathroom & 26D/26E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysTue 10/6/20Thu 10/15/20
12426D Bathroom & 26D/26E Kitchen & HVAC R#1-3Texture/Paint5 daysFri 10/16/20Thu 10/22/20
12526D Bathroom & 26D/26E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysFri 10/23/20Thu 11/12/20
12626D Bathroom & 26D/26E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysFri 11/13/20Tue 11/17/20
12725D Bathroom & 25D/25E Kitchen & HVAC R#1-335 daysThu 10/1/20Wed 11/18/20
12825D Bathroom & 25D/25E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 10/1/20Fri 10/2/20
12925D Bathroom & 25D/25E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 10/2/20Tue 10/6/20
13025D Bathroom & 25D/25E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 10/7/20Fri 10/16/20
13125D Bathroom & 25D/25E Kitchen & HVAC R#1-3Texture/Paint5 daysMon 10/19/20Fri 10/23/20
13225D Bathroom & 25D/25E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 10/26/20Fri 11/13/20
13325D Bathroom & 25D/25E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysMon 11/16/20Wed 11/18/20
13424D Bathroom & 24D/24E Kitchen & HVAC R#1-335 daysFri 10/2/20Thu 11/19/20
13524D Bathroom & 24D/24E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysFri 10/2/20Mon 10/5/20
13624D Bathroom & 24D/24E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 10/5/20Wed 10/7/20
13724D Bathroom & 24D/24E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysThu 10/8/20Mon 10/19/20
13824D Bathroom & 24D/24E Kitchen & HVAC R#1-3Texture/Paint5 daysTue 10/20/20Mon 10/26/20
13924D Bathroom & 24D/24E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 10/27/20Mon 11/16/20
14024D Bathroom & 24D/24E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysTue 11/17/20Thu 11/19/20
14123D Bathroom & 23D/23E Kitchen & HVAC R#1-335 daysMon 10/5/20Fri 11/20/20
14223D Bathroom & 23D/23E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysMon 10/5/20Tue 10/6/20
14323D Bathroom & 23D/23E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 10/6/20Thu 10/8/20
14423D Bathroom & 23D/23E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysFri 10/9/20Tue 10/20/20
14523D Bathroom & 23D/23E Kitchen & HVAC R#1-3Texture/Paint5 daysWed 10/21/20Tue 10/27/20
14623D Bathroom & 23D/23E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 10/28/20Tue 11/17/20
14723D Bathroom & 23D/23E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysWed 11/18/20Fri 11/20/20
14822D Bathroom & 22D/22E Kitchen & HVAC R#1-334 daysMon 10/12/20Mon 11/30/20
14922D Bathroom & 22D/22E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysMon 10/12/20Tue 10/13/20
15022D Bathroom & 22D/22E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 10/13/20Thu 10/15/20
15122D Bathroom & 22D/22E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysFri 10/16/20Tue 10/27/20
15222D Bathroom & 22D/22E Kitchen & HVAC R#1-3Texture/Paint5 daysWed 10/28/20Tue 11/3/20
15322D Bathroom & 22D/22E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 11/4/20Tue 11/24/20
15422D Bathroom & 22D/22E Kitchen & HVAC R#1-3Substantial Completion & Punchlist2 daysWed 11/25/20Mon 11/30/20
15521D Bathroom & 21D/21E Kitchen & HVAC R#1-335 daysTue 10/13/20Wed 12/2/20
15621D Bathroom & 21D/21E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysTue 10/13/20Wed 10/14/20
15721D Bathroom & 21D/21E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 10/14/20Fri 10/16/20
15821D Bathroom & 21D/21E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysMon 10/19/20Wed 10/28/20
15921D Bathroom & 21D/21E Kitchen & HVAC R#1-3Texture/Paint5 daysThu 10/29/20Wed 11/4/20
16021D Bathroom & 21D/21E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 11/5/20Wed 11/25/20
16121D Bathroom & 21D/21E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysMon 11/30/20Wed 12/2/20
16220D Bathroom & 20D/20E Kitchen35 daysWed 10/14/20Thu 12/3/20
16320D Bathroom & 20D/20E KitchenDemoltion & Abatement2 daysWed 10/14/20Thu 10/15/20
16420D Bathroom & 20D/20E KitchenPlumbing Replacement & Inspections3 daysThu 10/15/20Mon 10/19/20
16520D Bathroom & 20D/20E KitchenDrywall Repair & Inspections8 daysTue 10/20/20Thu 10/29/20
16620D Bathroom & 20D/20E KitchenTexture/Paint5 daysFri 10/30/20Thu 11/5/20
16720D Bathroom & 20D/20E KitchenTile, Carpentry & Reconstruction15 daysFri 11/6/20Mon 11/30/20
16820D Bathroom & 20D/20E KitchenSubstantial Completion & Punchlist3 daysTue 12/1/20Thu 12/3/20
16919D Bathroom & 19D/19E Kitchen & HVAC R#1-335 daysThu 10/15/20Fri 12/4/20
17019D Bathroom & 19D/19E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 10/15/20Fri 10/16/20
17119D Bathroom & 19D/19E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 10/16/20Tue 10/20/20
17219D Bathroom & 19D/19E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 10/21/20Fri 10/30/20
17319D Bathroom & 19D/19E Kitchen & HVAC R#1-3Texture/Paint5 daysMon 11/2/20Fri 11/6/20
17419D Bathroom & 19D/19E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 11/9/20Tue 12/1/20
17519D Bathroom & 19D/19E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysWed 12/2/20Fri 12/4/20
17618D Bathroom & 18D/18E Kitchen & HVAC R#1-335 daysFri 10/16/20Mon 12/7/20
17718D Bathroom & 18D/18E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysFri 10/16/20Mon 10/19/20
17818D Bathroom & 18D/18E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 10/19/20Wed 10/21/20
17918D Bathroom & 18D/18E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysThu 10/22/20Mon 11/2/20
18018D Bathroom & 18D/18E Kitchen & HVAC R#1-3Texture/Paint5 daysTue 11/3/20Mon 11/9/20
18118D Bathroom & 18D/18E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 11/10/20Wed 12/2/20
18218D Bathroom & 18D/18E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysThu 12/3/20Mon 12/7/20
18317D Bathroom & 17D/17E Kitchen & HVAC R#1-335 daysMon 10/19/20Tue 12/8/20
18417D Bathroom & 17D/17E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysMon 10/19/20Tue 10/20/20
18517D Bathroom & 17D/17E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 10/20/20Thu 10/22/20
18617D Bathroom & 17D/17E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysFri 10/23/20Tue 11/3/20
18717D Bathroom & 17D/17E Kitchen & HVAC R#1-3Texture/Paint5 daysWed 11/4/20Tue 11/10/20
18817D Bathroom & 17D/17E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 11/11/20Thu 12/3/20
18917D Bathroom & 17D/17E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysFri 12/4/20Tue 12/8/20
19016D Bathroom & 16D/16E Kitchen & HVAC R#1-335 daysTue 10/20/20Wed 12/9/20
19116D Bathroom & 16D/16E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysTue 10/20/20Wed 10/21/20
19216D Bathroom & 16D/16E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 10/21/20Fri 10/23/20
19316D Bathroom & 16D/16E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysMon 10/26/20Wed 11/4/20
19416D Bathroom & 16D/16E Kitchen & HVAC R#1-3Texture/Paint5 daysThu 11/5/20Wed 11/11/20
19516D Bathroom & 16D/16E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 11/12/20Fri 12/4/20
19616D Bathroom & 16D/16E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysMon 12/7/20Wed 12/9/20
19715D Bathroom & 15D/15E Kitchen & HVAC R#1-335 daysWed 10/21/20Thu 12/10/20
19815D Bathroom & 15D/15E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysWed 10/21/20Thu 10/22/20
19915D Bathroom & 15D/15E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 10/22/20Mon 10/26/20
20015D Bathroom & 15D/15E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysTue 10/27/20Thu 11/5/20
20115D Bathroom & 15D/15E Kitchen & HVAC R#1-3Texture/Paint5 daysFri 11/6/20Thu 11/12/20
20215D Bathroom & 15D/15E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysFri 11/13/20Mon 12/7/20
20315D Bathroom & 15D/15E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysTue 12/8/20Thu 12/10/20
20414D Bathroom & 14D/14E Kitchen & HVAC R#1-335 daysThu 10/22/20Fri 12/11/20
20514D Bathroom & 14D/14E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 10/22/20Fri 10/23/20
20614D Bathroom & 14D/14E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 10/23/20Tue 10/27/20
20714D Bathroom & 14D/14E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 10/28/20Fri 11/6/20
20814D Bathroom & 14D/14E Kitchen & HVAC R#1-3Texture/Paint5 daysMon 11/9/20Fri 11/13/20
20914D Bathroom & 14D/14E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 11/16/20Tue 12/8/20
21014D Bathroom & 14D/14E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysWed 12/9/20Fri 12/11/20
21113D Bathroom & 13D/13E Kitchen & HVAC R#1-335 daysFri 10/23/20Mon 12/14/20
21213D Bathroom & 13D/13E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysFri 10/23/20Mon 10/26/20
21313D Bathroom & 13D/13E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 10/26/20Wed 10/28/20
21413D Bathroom & 13D/13E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysThu 10/29/20Mon 11/9/20
21513D Bathroom & 13D/13E Kitchen & HVAC R#1-3Texture/Paint5 daysTue 11/10/20Mon 11/16/20
21613D Bathroom & 13D/13E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 11/17/20Wed 12/9/20
21713D Bathroom & 13D/13E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysThu 12/10/20Mon 12/14/20
21812D Bathroom & 12D/12E Kitchen & HVAC R#1-335 daysMon 10/26/20Tue 12/15/20
21912D Bathroom & 12D/12E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysMon 10/26/20Tue 10/27/20
22012D Bathroom & 12D/12E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 10/27/20Thu 10/29/20
22112D Bathroom & 12D/12E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysFri 10/30/20Tue 11/10/20
22212D Bathroom & 12D/12E Kitchen & HVAC R#1-3Texture/Paint5 daysWed 11/11/20Tue 11/17/20
22312D Bathroom & 12D/12E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 11/18/20Thu 12/10/20
22412D Bathroom & 12D/12E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysFri 12/11/20Tue 12/15/20
22511D Bathroom & 11D/11E Kitchen & HVAC R#1-335 daysTue 10/27/20Wed 12/16/20
22611D Bathroom & 11D/11E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysTue 10/27/20Wed 10/28/20
22711D Bathroom & 11D/11E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 10/28/20Fri 10/30/20
22811D Bathroom & 11D/11E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysMon 11/2/20Wed 11/11/20
22911D Bathroom & 11D/11E Kitchen & HVAC R#1-3Texture/Paint5 daysThu 11/12/20Wed 11/18/20
23011D Bathroom & 11D/11E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 11/19/20Fri 12/11/20
23111D Bathroom & 11D/11E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysMon 12/14/20Wed 12/16/20
23210D Bathroom & 10D/10E Kitchen & HVAC R#1-335 daysWed 10/28/20Thu 12/17/20
23310D Bathroom & 10D/10E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysWed 10/28/20Thu 10/29/20
23410D Bathroom & 10D/10E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 10/29/20Mon 11/2/20
23510D Bathroom & 10D/10E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysTue 11/3/20Thu 11/12/20
23610D Bathroom & 10D/10E Kitchen & HVAC R#1-3Texture/Paint5 daysFri 11/13/20Thu 11/19/20
23710D Bathroom & 10D/10E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysFri 11/20/20Mon 12/14/20
23810D Bathroom & 10D/10E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysTue 12/15/20Thu 12/17/20
2399D Bathroom & 9D/9E Kitchen & HVAC R#1-335 daysThu 10/29/20Fri 12/18/20
2409D Bathroom & 9D/9E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 10/29/20Fri 10/30/20
2419D Bathroom & 9D/9E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 10/30/20Tue 11/3/20
2429D Bathroom & 9D/9E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 11/4/20Fri 11/13/20
2439D Bathroom & 9D/9E Kitchen & HVAC R#1-3Texture/Paint5 daysMon 11/16/20Fri 11/20/20
2449D Bathroom & 9D/9E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 11/23/20Tue 12/15/20
2459D Bathroom & 9D/9E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysWed 12/16/20Fri 12/18/20
2468D Bathroom & 8D/8E Kitchen & HVAC R#1-335 daysFri 10/30/20Mon 1/4/21
2478D Bathroom & 8D/8E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysFri 10/30/20Mon 11/2/20
2488D Bathroom & 8D/8E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 11/2/20Wed 11/4/20
2498D Bathroom & 8D/8E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysThu 11/5/20Mon 11/16/20
2508D Bathroom & 8D/8E Kitchen & HVAC R#1-3Texture/Paint5 daysTue 11/17/20Mon 11/23/20
2518D Bathroom & 8D/8E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 11/24/20Wed 12/16/20
2528D Bathroom & 8D/8E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysThu 12/17/20Mon 1/4/21
2537D Bathroom & 7D/7E Kitchen & HVAC R#1-335 daysMon 11/2/20Tue 1/5/21
2547D Bathroom & 7D/7E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysMon 11/2/20Tue 11/3/20
2557D Bathroom & 7D/7E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysTue 11/3/20Thu 11/5/20
2567D Bathroom & 7D/7E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysFri 11/6/20Tue 11/17/20
2577D Bathroom & 7D/7E Kitchen & HVAC R#1-3Texture/Paint5 daysWed 11/18/20Tue 11/24/20
2587D Bathroom & 7D/7E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 11/25/20Thu 12/17/20
2597D Bathroom & 7D/7E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysFri 12/18/20Tue 1/5/21
2606D Bathroom & 6D/6E Kitchen & HVAC R#1-335 daysTue 11/3/20Wed 1/6/21
2616D Bathroom & 6D/6E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysTue 11/3/20Wed 11/4/20
2626D Bathroom & 6D/6E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysWed 11/4/20Fri 11/6/20
2636D Bathroom & 6D/6E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysMon 11/9/20Wed 11/18/20
2646D Bathroom & 6D/6E Kitchen & HVAC R#1-3Texture/Paint5 daysThu 11/19/20Wed 11/25/20
2656D Bathroom & 6D/6E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysMon 11/30/20Fri 12/18/20
2666D Bathroom & 6D/6E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysMon 1/4/21Wed 1/6/21
2675D Bathroom & 5D/5E Kitchen & HVAC R#1-335 daysWed 11/4/20Thu 1/7/21
2685D Bathroom & 5D/5E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysWed 11/4/20Thu 11/5/20
2695D Bathroom & 5D/5E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysThu 11/5/20Mon 11/9/20
2705D Bathroom & 5D/5E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysTue 11/10/20Thu 11/19/20
2715D Bathroom & 5D/5E Kitchen & HVAC R#1-3Texture/Paint5 daysFri 11/20/20Mon 11/30/20
2725D Bathroom & 5D/5E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysTue 12/1/20Mon 1/4/21
2735D Bathroom & 5D/5E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysTue 1/5/21Thu 1/7/21
2744D Bathroom & 4D/4E Kitchen & HVAC R#1-335 daysThu 11/5/20Fri 1/8/21
2754D Bathroom & 4D/4E Kitchen & HVAC R#1-3Demoltion & Abatement2 daysThu 11/5/20Fri 11/6/20
2764D Bathroom & 4D/4E Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysFri 11/6/20Tue 11/10/20
2774D Bathroom & 4D/4E Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysWed 11/11/20Fri 11/20/20
2784D Bathroom & 4D/4E Kitchen & HVAC R#1-3Texture/Paint5 daysMon 11/23/20Tue 12/1/20
2794D Bathroom & 4D/4E Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysWed 12/2/20Tue 1/5/21
2804D Bathroom & 4D/4E Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysWed 1/6/21Fri 1/8/21
2813 Residents Room Bathrooms & Kitchen & HVAC R#1-335 daysFri 11/6/20Mon 1/11/21
2823 Residents Room Bathrooms & Kitchen & HVAC R#1-3Demoltion & Abatement2 daysFri 11/6/20Mon 11/9/20
2833 Residents Room Bathrooms & Kitchen & HVAC R#1-3Plumbing Replacement & Inspections3 daysMon 11/9/20Wed 11/11/20
2843 Residents Room Bathrooms & Kitchen & HVAC R#1-3Drywall Repair & Inspections8 daysThu 11/12/20Mon 11/23/20
2853 Residents Room Bathrooms & Kitchen & HVAC R#1-3Texture/Paint5 daysTue 11/24/20Wed 12/2/20
2863 Residents Room Bathrooms & Kitchen & HVAC R#1-3Tile, Carpentry & Reconstruction15 daysThu 12/3/20Wed 1/6/21
2873 Residents Room Bathrooms & Kitchen & HVAC R#1-3Substantial Completion & Punchlist3 daysThu 1/7/21Mon 1/11/21
28836K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L Kitchen9 daysMon 11/9/20Thu 11/19/20
28936K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L KitchenDemo drywall1 dayMon 11/9/20Mon 11/9/20
29036K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L KitchenPlumbing connection1 dayTue 11/10/20Tue 11/10/20
29136K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L KitchenDrywall Repari3 daysWed 11/11/20Fri 11/13/20
29236K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L KitchenTexture Paint2 daysMon 11/16/20Tue 11/17/20
29336K Bathroom & 36J/K Kitchen & 41K Dining Room / 41L KitchenSubstantial Completion & Punchlist2 daysWed 11/18/20Thu 11/19/20
29435K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L Kitchen35 daysMon 11/9/20Tue 1/12/21
29535K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L KitchenDemoltion & Abatement2 daysMon 11/9/20Tue 11/10/20
29635K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L KitchenPlumbing Replacement & Inspections2 daysWed 11/11/20Thu 11/12/20
29735K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L KitchenDrywall Repair & Inspections8 daysFri 11/13/20Tue 11/24/20
29835K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L KitchenTexture/Paint6 daysWed 11/25/20Fri 12/4/20
29935K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L KitchenTile, Carpentry & Reconstruction15 daysMon 12/7/20Fri 1/8/21
30035K Bathroom & 35J/K Kitchen & 40K Dining Room / 40L KitchenSubstantial Completion & Punchlist2 daysMon 1/11/21Tue 1/12/21
30134K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L Kitchen36 daysTue 11/10/20Thu 1/14/21
30234K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L KitchenDemoltion & Abatement2 daysTue 11/10/20Wed 11/11/20
30334K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L KitchenPlumbing Replacement & Inspections3 daysThu 11/12/20Mon 11/16/20
30434K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L KitchenDrywall Repair & Inspections8 daysTue 11/17/20Mon 11/30/20
30534K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L KitchenTexture/Paint6 daysTue 12/1/20Tue 12/8/20
30634K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L KitchenTile, Carpentry & Reconstruction15 daysWed 12/9/20Tue 1/12/21
30734K Bathroom & 34J/K Kitchen & 39K Dining Room / 39L KitchenSubstantial Completion & Punchlist2 daysWed 1/13/21Thu 1/14/21
30833K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L Kitchen36 daysTue 11/10/20Thu 1/14/21
30933K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L KitchenDemoltion & Abatement2 daysTue 11/10/20Wed 11/11/20
31033K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L KitchenPlumbing Replacement & Inspections3 daysThu 11/12/20Mon 11/16/20
31133K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L KitchenDrywall Repair & Inspections8 daysTue 11/17/20Mon 11/30/20
31233K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L KitchenTexture/Paint6 daysTue 12/1/20Tue 12/8/20
31333K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L KitchenTile, Carpentry & Reconstruction15 daysWed 12/9/20Tue 1/12/21
31433K Bathroom & 33J/K Kitchen & 37K Dining Room / 37L KitchenSubstantial Completion & Punchlist2 daysWed 1/13/21Thu 1/14/21
31532K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L Kitchen36 daysWed 11/11/20Fri 1/15/21
31632K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L KitchenDemoltion & Abatement2 daysWed 11/11/20Thu 11/12/20
31732K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L KitchenPlumbing Replacement & Inspections3 daysFri 11/13/20Tue 11/17/20
31832K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L KitchenDrywall Repair & Inspections8 daysWed 11/18/20Tue 12/1/20
31932K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L KitchenTexture/Paint6 daysWed 12/2/20Wed 12/9/20
32032K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L KitchenTile, Carpentry & Reconstruction15 daysThu 12/10/20Wed 1/13/21
32132K Bathroom & 32J/K Kitchen & 36K Dining Room / 36L KitchenSubstantial Completion & Punchlist2 daysThu 1/14/21Fri 1/15/21
32231K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L Kitchen36 daysWed 11/11/20Fri 1/15/21
32331K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L KitchenDemoltion & Abatement2 daysWed 11/11/20Thu 11/12/20
32431K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L KitchenPlumbing Replacement & Inspections3 daysFri 11/13/20Tue 11/17/20
32531K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L KitchenDrywall Repair & Inspections8 daysWed 11/18/20Tue 12/1/20
32631K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L KitchenTexture/Paint6 daysWed 12/2/20Wed 12/9/20
32731K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L KitchenTile, Carpentry & Reconstruction15 daysThu 12/10/20Wed 1/13/21
32831K Bathroom & 31J/K Kitchen & 35K Dining Room / 35L KitchenSubstantial Completion & Punchlist2 daysThu 1/14/21Fri 1/15/21
32930K Bathroom & 30J/K Kitchen36 daysThu 11/12/20Mon 1/18/21
33030K Bathroom & 30J/K KitchenDemoltion & Abatement2 daysThu 11/12/20Fri 11/13/20
33130K Bathroom & 30J/K KitchenPlumbing Replacement & Inspections3 daysMon 11/16/20Wed 11/18/20
33230K Bathroom & 30J/K KitchenDrywall Repair & Inspections8 daysThu 11/19/20Wed 12/2/20
33330K Bathroom & 30J/K KitchenTexture/Paint6 daysThu 12/3/20Thu 12/10/20
33430K Bathroom & 30J/K KitchenTile, Carpentry & Reconstruction15 daysFri 12/11/20Thu 1/14/21
33530K Bathroom & 30J/K KitchenSubstantial Completion & Punchlist2 daysFri 1/15/21Mon 1/18/21
33629K Bathroom & 29J/K Kitchen36 daysThu 11/12/20Mon 1/18/21
33729K Bathroom & 29J/K KitchenDemoltion & Abatement2 daysThu 11/12/20Fri 11/13/20
33829K Bathroom & 29J/K KitchenPlumbing Replacement & Inspections3 daysMon 11/16/20Wed 11/18/20
33929K Bathroom & 29J/K KitchenDrywall Repair & Inspections8 daysThu 11/19/20Wed 12/2/20
34029K Bathroom & 29J/K KitchenTexture/Paint6 daysThu 12/3/20Thu 12/10/20
34129K Bathroom & 29J/K KitchenTile, Carpentry & Reconstruction15 daysFri 12/11/20Thu 1/14/21
34229K Bathroom & 29J/K KitchenSubstantial Completion & Punchlist2 daysFri 1/15/21Mon 1/18/21
34328K Bathroom & 28J/K Kitchen36 daysFri 11/13/20Tue 1/19/21
34428K Bathroom & 28J/K KitchenDemoltion & Abatement2 daysFri 11/13/20Mon 11/16/20
34528K Bathroom & 28J/K KitchenPlumbing Replacement & Inspections3 daysTue 11/17/20Thu 11/19/20
34628K Bathroom & 28J/K KitchenDrywall Repair & Inspections8 daysFri 11/20/20Thu 12/3/20
34728K Bathroom & 28J/K KitchenTexture/Paint6 daysFri 12/4/20Fri 12/11/20
34828K Bathroom & 28J/K KitchenTile, Carpentry & Reconstruction15 daysMon 12/14/20Fri 1/15/21
34928K Bathroom & 28J/K KitchenSubstantial Completion & Punchlist2 daysMon 1/18/21Tue 1/19/21
35027K Bathroom & 27J/K Kitchen36 daysFri 11/13/20Tue 1/19/21
35127K Bathroom & 27J/K KitchenDemoltion & Abatement2 daysFri 11/13/20Mon 11/16/20
35227K Bathroom & 27J/K KitchenPlumbing Replacement & Inspections3 daysTue 11/17/20Thu 11/19/20
35327K Bathroom & 27J/K KitchenDrywall Repair & Inspections8 daysFri 11/20/20Thu 12/3/20
35427K Bathroom & 27J/K KitchenTexture/Paint6 daysFri 12/4/20Fri 12/11/20
35527K Bathroom & 27J/K KitchenTile, Carpentry & Reconstruction15 daysMon 12/14/20Fri 1/15/21
35627K Bathroom & 27J/K KitchenSubstantial Completion & Punchlist2 daysMon 1/18/21Tue 1/19/21
35726K Bathroom & 26J/K Kitchen36 daysMon 11/16/20Wed 1/20/21
35826K Bathroom & 26J/K KitchenDemoltion & Abatement2 daysMon 11/16/20Tue 11/17/20
35926K Bathroom & 26J/K KitchenPlumbing Replacement & Inspections3 daysWed 11/18/20Fri 11/20/20
36026K Bathroom & 26J/K KitchenDrywall Repair & Inspections8 daysMon 11/23/20Fri 12/4/20
36126K Bathroom & 26J/K KitchenTexture/Paint6 daysMon 12/7/20Mon 12/14/20
36226K Bathroom & 26J/K KitchenTile, Carpentry & Reconstruction15 daysTue 12/15/20Mon 1/18/21
36326K Bathroom & 26J/K KitchenSubstantial Completion & Punchlist2 daysTue 1/19/21Wed 1/20/21
36425K Bathroom & 25J/K Kitchen36 daysMon 11/16/20Wed 1/20/21
36525K Bathroom & 25J/K KitchenDemoltion & Abatement2 daysMon 11/16/20Tue 11/17/20
36625K Bathroom & 25J/K KitchenPlumbing Replacement & Inspections3 daysWed 11/18/20Fri 11/20/20
36725K Bathroom & 25J/K KitchenDrywall Repair & Inspections8 daysMon 11/23/20Fri 12/4/20
36825K Bathroom & 25J/K KitchenTexture/Paint6 daysMon 12/7/20Mon 12/14/20
36925K Bathroom & 25J/K KitchenTile, Carpentry & Reconstruction15 daysTue 12/15/20Mon 1/18/21
37025K Bathroom & 25J/K KitchenSubstantial Completion & Punchlist2 daysTue 1/19/21Wed 1/20/21
37124K Bathroom & 24J/K Kitchen36 daysTue 11/17/20Thu 1/21/21
37224K Bathroom & 24J/K KitchenDemoltion & Abatement2 daysTue 11/17/20Wed 11/18/20
37324K Bathroom & 24J/K KitchenPlumbing Replacement & Inspections3 daysThu 11/19/20Mon 11/23/20
37424K Bathroom & 24J/K KitchenDrywall Repair & Inspections8 daysTue 11/24/20Mon 12/7/20
37524K Bathroom & 24J/K KitchenTexture/Paint6 daysTue 12/8/20Tue 12/15/20
37624K Bathroom & 24J/K KitchenTile, Carpentry & Reconstruction15 daysWed 12/16/20Tue 1/19/21
37724K Bathroom & 24J/K KitchenSubstantial Completion & Punchlist2 daysWed 1/20/21Thu 1/21/21
37823K Bathroom & 23J/K Kitchen36 daysTue 11/17/20Thu 1/21/21
37923K Bathroom & 23J/K KitchenDemoltion & Abatement2 daysTue 11/17/20Wed 11/18/20
38023K Bathroom & 23J/K KitchenPlumbing Replacement & Inspections3 daysThu 11/19/20Mon 11/23/20
38123K Bathroom & 23J/K KitchenDrywall Repair & Inspections8 daysTue 11/24/20Mon 12/7/20
38223K Bathroom & 23J/K KitchenTexture/Paint6 daysTue 12/8/20Tue 12/15/20
38323K Bathroom & 23J/K KitchenTile, Carpentry & Reconstruction15 daysWed 12/16/20Tue 1/19/21
38423K Bathroom & 23J/K KitchenSubstantial Completion & Punchlist2 daysWed 1/20/21Thu 1/21/21
38522K Bathroom & 22J/K Kitchen36 daysWed 11/18/20Fri 1/22/21
38622K Bathroom & 22J/K KitchenDemoltion & Abatement2 daysWed 11/18/20Thu 11/19/20
38722K Bathroom & 22J/K KitchenPlumbing Replacement & Inspections3 daysFri 11/20/20Tue 11/24/20
38822K Bathroom & 22J/K KitchenDrywall Repair & Inspections8 daysWed 11/25/20Tue 12/8/20
38922K Bathroom & 22J/K KitchenTexture/Paint6 daysWed 12/9/20Wed 12/16/20
39022K Bathroom & 22J/K KitchenTile, Carpentry & Reconstruction15 daysThu 12/17/20Wed 1/20/21
39122K Bathroom & 22J/K KitchenSubstantial Completion & Punchlist2 daysThu 1/21/21Fri 1/22/21
39221K Bathroom & 21J/K Kitchen36 daysWed 11/18/20Fri 1/22/21
39321K Bathroom & 21J/K KitchenDemoltion & Abatement2 daysWed 11/18/20Thu 11/19/20
39421K Bathroom & 21J/K KitchenPlumbing Replacement & Inspections3 daysFri 11/20/20Tue 11/24/20
39521K Bathroom & 21J/K KitchenDrywall Repair & Inspections8 daysWed 11/25/20Tue 12/8/20
39621K Bathroom & 21J/K KitchenTexture/Paint6 daysWed 12/9/20Wed 12/16/20
39721K Bathroom & 21J/K KitchenTile, Carpentry & Reconstruction15 daysThu 12/17/20Wed 1/20/21
39821K Bathroom & 21J/K KitchenSubstantial Completion & Punchlist2 daysThu 1/21/21Fri 1/22/21
39920K Bathroom & 20J/K Kitchen36 daysThu 11/19/20Mon 1/25/21
40020K Bathroom & 20J/K KitchenDemoltion & Abatement2 daysThu 11/19/20Fri 11/20/20
40120K Bathroom & 20J/K KitchenPlumbing Replacement & Inspections3 daysMon 11/23/20Wed 11/25/20
40220K Bathroom & 20J/K KitchenDrywall Repair & Inspections8 daysMon 11/30/20Wed 12/9/20
40320K Bathroom & 20J/K KitchenTexture/Paint6 daysThu 12/10/20Thu 12/17/20
40420K Bathroom & 20J/K KitchenTile, Carpentry & Reconstruction15 daysFri 12/18/20Thu 1/21/21
40520K Bathroom & 20J/K KitchenSubstantial Completion & Punchlist2 daysFri 1/22/21Mon 1/25/21
40619K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L Kitchen36 daysThu 11/19/20Mon 1/25/21
40719K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L KitchenDemoltion & Abatement2 daysThu 11/19/20Fri 11/20/20
40819K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L KitchenPlumbing Replacement & Inspections3 daysMon 11/23/20Wed 11/25/20
40919K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L KitchenDrywall Repair & Inspections8 daysMon 11/30/20Wed 12/9/20
41019K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L KitchenTexture/Paint6 daysThu 12/10/20Thu 12/17/20
41119K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L KitchenTile, Carpentry & Reconstruction15 daysFri 12/18/20Thu 1/21/21
41219K Bathroom & 19J/K Kitchen & 19K Dining Room / 19L KitchenSubstantial Completion & Punchlist2 daysFri 1/22/21Mon 1/25/21
41318K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L Kitchen36 daysFri 11/20/20Tue 1/26/21
41418K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L KitchenDemoltion & Abatement2 daysFri 11/20/20Mon 11/23/20
41518K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L KitchenPlumbing Replacement & Inspections3 daysTue 11/24/20Mon 11/30/20
41618K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L KitchenDrywall Repair & Inspections8 daysTue 12/1/20Thu 12/10/20
41718K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L KitchenTexture/Paint6 daysFri 12/11/20Fri 12/18/20
41818K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L KitchenTile, Carpentry & Reconstruction15 daysMon 1/4/21Fri 1/22/21
41918K Bathroom & 18J/K Kitchen & 18K Dining Room / 18L KitchenSubstantial Completion & Punchlist2 daysMon 1/25/21Tue 1/26/21
42017K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L Kitchen36 daysFri 11/20/20Tue 1/26/21
42117K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L KitchenDemoltion & Abatement2 daysFri 11/20/20Mon 11/23/20
42217K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L KitchenPlumbing Replacement & Inspections3 daysTue 11/24/20Mon 11/30/20
42317K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L KitchenDrywall Repair & Inspections8 daysTue 12/1/20Thu 12/10/20
42417K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L KitchenTexture/Paint6 daysFri 12/11/20Fri 12/18/20
42517K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L KitchenTile, Carpentry & Reconstruction15 daysMon 1/4/21Fri 1/22/21
42617K Bathroom & 17J/K Kitchen & 17K Dining Room / 17L KitchenSubstantial Completion & Punchlist2 daysMon 1/25/21Tue 1/26/21
42716K Bathroom & 16J/K Kitchen36 daysMon 11/23/20Wed 1/27/21
42816K Bathroom & 16J/K KitchenDemoltion & Abatement2 daysMon 11/23/20Tue 11/24/20
42916K Bathroom & 16J/K KitchenPlumbing Replacement & Inspections3 daysWed 11/25/20Tue 12/1/20
43016K Bathroom & 16J/K KitchenDrywall Repair & Inspections8 daysWed 12/2/20Fri 12/11/20
43116K Bathroom & 16J/K KitchenTexture/Paint6 daysMon 12/14/20Mon 1/4/21
43216K Bathroom & 16J/K KitchenTile, Carpentry & Reconstruction15 daysTue 1/5/21Mon 1/25/21
43316K Bathroom & 16J/K KitchenSubstantial Completion & Punchlist2 daysTue 1/26/21Wed 1/27/21
43415K Bathroom & 15J/K Kitchen36 daysMon 11/23/20Wed 1/27/21
43515K Bathroom & 15J/K KitchenDemoltion & Abatement2 daysMon 11/23/20Tue 11/24/20
43615K Bathroom & 15J/K KitchenPlumbing Replacement & Inspections3 daysWed 11/25/20Tue 12/1/20
43715K Bathroom & 15J/K KitchenDrywall Repair & Inspections8 daysWed 12/2/20Fri 12/11/20
43815K Bathroom & 15J/K KitchenTexture/Paint6 daysMon 12/14/20Mon 1/4/21
43915K Bathroom & 15J/K KitchenTile, Carpentry & Reconstruction15 daysTue 1/5/21Mon 1/25/21
44015K Bathroom & 15J/K KitchenSubstantial Completion & Punchlist2 daysTue 1/26/21Wed 1/27/21
44114K Bathroom & 14J/K Kitchen36 daysTue 11/24/20Thu 1/28/21
44214K Bathroom & 14J/K KitchenDemoltion & Abatement2 daysTue 11/24/20Wed 11/25/20
44314K Bathroom & 14J/K KitchenPlumbing Replacement & Inspections3 daysMon 11/30/20Wed 12/2/20
44414K Bathroom & 14J/K KitchenDrywall Repair & Inspections8 daysThu 12/3/20Mon 12/14/20
44514K Bathroom & 14J/K KitchenTexture/Paint6 daysTue 12/15/20Tue 1/5/21
44614K Bathroom & 14J/K KitchenTile, Carpentry & Reconstruction15 daysWed 1/6/21Tue 1/26/21
44714K Bathroom & 14J/K KitchenSubstantial Completion & Punchlist2 daysWed 1/27/21Thu 1/28/21
44813K Bathroom & 13J/K Kitchen36 daysTue 11/24/20Thu 1/28/21
44913K Bathroom & 13J/K KitchenDemoltion & Abatement2 daysTue 11/24/20Wed 11/25/20
45013K Bathroom & 13J/K KitchenPlumbing Replacement & Inspections3 daysMon 11/30/20Wed 12/2/20
45113K Bathroom & 13J/K KitchenDrywall Repair & Inspections8 daysThu 12/3/20Mon 12/14/20
45213K Bathroom & 13J/K KitchenTexture/Paint6 daysTue 12/15/20Tue 1/5/21
45313K Bathroom & 13J/K KitchenTile, Carpentry & Reconstruction15 daysWed 1/6/21Tue 1/26/21
45413K Bathroom & 13J/K KitchenSubstantial Completion & Punchlist2 daysWed 1/27/21Thu 1/28/21
45512K Bathroom & 12J/K Kitchen36 daysWed 11/25/20Fri 1/29/21
45612K Bathroom & 12J/K KitchenDemoltion & Abatement2 daysWed 11/25/20Mon 11/30/20
45712K Bathroom & 12J/K KitchenPlumbing Replacement & Inspections3 daysTue 12/1/20Thu 12/3/20
45812K Bathroom & 12J/K KitchenDrywall Repair & Inspections8 daysFri 12/4/20Tue 12/15/20
45912K Bathroom & 12J/K KitchenTexture/Paint6 daysWed 12/16/20Wed 1/6/21
46012K Bathroom & 12J/K KitchenTile, Carpentry & Reconstruction15 daysThu 1/7/21Wed 1/27/21
46112K Bathroom & 12J/K KitchenSubstantial Completion & Punchlist2 daysThu 1/28/21Fri 1/29/21
46211K Bathroom & 11J/K Kitchen36 daysWed 11/25/20Fri 1/29/21
46311K Bathroom & 11J/K KitchenDemoltion & Abatement2 daysWed 11/25/20Mon 11/30/20
46411K Bathroom & 11J/K KitchenPlumbing Replacement & Inspections3 daysTue 12/1/20Thu 12/3/20
46511K Bathroom & 11J/K KitchenDrywall Repair & Inspections8 daysFri 12/4/20Tue 12/15/20
46611K Bathroom & 11J/K KitchenTexture/Paint6 daysWed 12/16/20Wed 1/6/21
46711K Bathroom & 11J/K KitchenTile, Carpentry & Reconstruction15 daysThu 1/7/21Wed 1/27/21
46811K Bathroom & 11J/K KitchenSubstantial Completion & Punchlist2 daysThu 1/28/21Fri 1/29/21
46910K Bathroom & 10J/K Kitchen36 daysMon 11/30/20Mon 2/1/21
47010K Bathroom & 10J/K KitchenDemoltion & Abatement2 daysMon 11/30/20Tue 12/1/20
47110K Bathroom & 10J/K KitchenPlumbing Replacement & Inspections3 daysWed 12/2/20Fri 12/4/20
47210K Bathroom & 10J/K KitchenDrywall Repair & Inspections8 daysMon 12/7/20Wed 12/16/20
47310K Bathroom & 10J/K KitchenTexture/Paint6 daysThu 12/17/20Thu 1/7/21
47410K Bathroom & 10J/K KitchenTile, Carpentry & Reconstruction15 daysFri 1/8/21Thu 1/28/21
47510K Bathroom & 10J/K KitchenSubstantial Completion & Punchlist2 daysFri 1/29/21Mon 2/1/21
4769K Bathroom & 9J/K Kitchen36 daysMon 11/30/20Mon 2/1/21
4779K Bathroom & 9J/K KitchenDemoltion & Abatement2 daysMon 11/30/20Tue 12/1/20
4789K Bathroom & 9J/K KitchenPlumbing Replacement & Inspections3 daysWed 12/2/20Fri 12/4/20
4799K Bathroom & 9J/K KitchenDrywall Repair & Inspections8 daysMon 12/7/20Wed 12/16/20
4809K Bathroom & 9J/K KitchenTexture/Paint6 daysThu 12/17/20Thu 1/7/21
4819K Bathroom & 9J/K KitchenTile, Carpentry & Reconstruction15 daysFri 1/8/21Thu 1/28/21
4829K Bathroom & 9J/K KitchenSubstantial Completion & Punchlist2 daysFri 1/29/21Mon 2/1/21
4838K Bathroom & 8J/K Kitchen36 daysTue 12/1/20Tue 2/2/21
4848K Bathroom & 8J/K KitchenDemoltion & Abatement2 daysTue 12/1/20Wed 12/2/20
4858K Bathroom & 8J/K KitchenPlumbing Replacement & Inspections3 daysThu 12/3/20Mon 12/7/20
4868K Bathroom & 8J/K KitchenDrywall Repair & Inspections8 daysTue 12/8/20Thu 12/17/20
4878K Bathroom & 8J/K KitchenTexture/Paint6 daysFri 12/18/20Fri 1/8/21
4888K Bathroom & 8J/K KitchenTile, Carpentry & Reconstruction15 daysMon 1/11/21Fri 1/29/21
4898K Bathroom & 8J/K KitchenSubstantial Completion & Punchlist2 daysMon 2/1/21Tue 2/2/21
4907K Bathroom & 7J/K Kitchen36 daysTue 12/1/20Tue 2/2/21
4917K Bathroom & 7J/K KitchenDemoltion & Abatement2 daysTue 12/1/20Wed 12/2/20
4927K Bathroom & 7J/K KitchenPlumbing Replacement & Inspections3 daysThu 12/3/20Mon 12/7/20
4937K Bathroom & 7J/K KitchenDrywall Repair & Inspections8 daysTue 12/8/20Thu 12/17/20
4947K Bathroom & 7J/K KitchenTexture/Paint6 daysFri 12/18/20Fri 1/8/21
4957K Bathroom & 7J/K KitchenTile, Carpentry & Reconstruction15 daysMon 1/11/21Fri 1/29/21
4967K Bathroom & 7J/K KitchenSubstantial Completion & Punchlist2 daysMon 2/1/21Tue 2/2/21
4976K Bathroom & 6J/K Kitchen36 daysWed 12/2/20Wed 2/3/21
4986K Bathroom & 6J/K KitchenDemoltion & Abatement2 daysWed 12/2/20Thu 12/3/20
4996K Bathroom & 6J/K KitchenPlumbing Replacement & Inspections3 daysFri 12/4/20Tue 12/8/20
5006K Bathroom & 6J/K KitchenDrywall Repair & Inspections8 daysWed 12/9/20Fri 12/18/20
5016K Bathroom & 6J/K KitchenTexture/Paint6 daysMon 1/4/21Mon 1/11/21
5026K Bathroom & 6J/K KitchenTile, Carpentry & Reconstruction15 daysTue 1/12/21Mon 2/1/21
5036K Bathroom & 6J/K KitchenSubstantial Completion & Punchlist2 daysTue 2/2/21Wed 2/3/21
5045K Bathroom & 5J/K Kitchen36 daysWed 12/2/20Wed 2/3/21
5055K Bathroom & 5J/K KitchenDemoltion & Abatement2 daysWed 12/2/20Thu 12/3/20
5065K Bathroom & 5J/K KitchenPlumbing Replacement & Inspections3 daysFri 12/4/20Tue 12/8/20
5075K Bathroom & 5J/K KitchenDrywall Repair & Inspections8 daysWed 12/9/20Fri 12/18/20
5085K Bathroom & 5J/K KitchenTexture/Paint6 daysMon 1/4/21Mon 1/11/21
5095K Bathroom & 5J/K KitchenTile, Carpentry & Reconstruction15 daysTue 1/12/21Mon 2/1/21
5105K Bathroom & 5J/K KitchenSubstantial Completion & Punchlist2 daysTue 2/2/21Wed 2/3/21
5114K Bathroom & 4J/K Kitchen36 daysThu 12/3/20Thu 2/4/21
5124K Bathroom & 4J/K KitchenDemoltion & Abatement2 daysThu 12/3/20Fri 12/4/20
5134K Bathroom & 4J/K KitchenPlumbing Replacement & Inspections3 daysMon 12/7/20Wed 12/9/20
5144K Bathroom & 4J/K KitchenDrywall Repair & Inspections8 daysThu 12/10/20Mon 1/4/21
5154K Bathroom & 4J/K KitchenTexture/Paint6 daysTue 1/5/21Tue 1/12/21
5164K Bathroom & 4J/K KitchenTile, Carpentry & Reconstruction15 daysWed 1/13/21Tue 2/2/21
5174K Bathroom & 4J/K KitchenSubstantial Completion & Punchlist2 daysWed 2/3/21Thu 2/4/21
5183E Bathroom & 3D/E Kitchen36 daysThu 12/3/20Thu 2/4/21
5193E Bathroom & 3D/E KitchenDemoltion & Abatement2 daysThu 12/3/20Fri 12/4/20
5203E Bathroom & 3D/E KitchenPlumbing Replacement & Inspections3 daysMon 12/7/20Wed 12/9/20
5213E Bathroom & 3D/E KitchenDrywall Repair & Inspections8 daysThu 12/10/20Mon 1/4/21
5223E Bathroom & 3D/E KitchenTexture/Paint6 daysTue 1/5/21Tue 1/12/21
5233E Bathroom & 3D/E KitchenTile, Carpentry & Reconstruction15 daysWed 1/13/21Tue 2/2/21
5243E Bathroom & 3D/E KitchenSubstantial Completion & Punchlist2 daysWed 2/3/21Thu 2/4/21
525Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICE17 daysFri 12/4/20Mon 1/11/21
526Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICEDrywall Abatement13 daysFri 12/4/20Tue 1/5/21
527Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICEDemolish old piping-Riser Outage13 daysMon 12/7/20Wed 1/6/21
528Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICEInstall New Piping13 daysMon 12/7/20Wed 1/6/21
529Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICETest/Insulate13 daysTue 12/8/20Thu 1/7/21
530Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICERestore Service1 dayThu 1/7/21Thu 1/7/21
531Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICEDrywall Repair/Paint14 daysTue 12/8/20Fri 1/8/21
532Riser #1-2 Replacement, E Hall Closet 41st-3rd (C Hall Closet)-OUT OF SERVICESubstantial Completion1 dayMon 1/11/21Mon 1/11/21
533Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICE12 daysWed 1/6/21Thu 1/21/21
534Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICEDrywall Abatement8 daysWed 1/6/21Fri 1/15/21
535Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICEDemolish old piping-Riser Outage8 daysThu 1/7/21Mon 1/18/21
536Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICEInstall New Piping8 daysThu 1/7/21Mon 1/18/21
537Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICETest/Insulate8 daysFri 1/8/21Tue 1/19/21
538Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICERestore Service1 dayTue 1/19/21Tue 1/19/21
539Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICEDrywall Repair/Paint9 daysFri 1/8/21Wed 1/20/21
540Riser #5-2 Replacement, J Hall Closet 41st-18th (L Hall Closet)-OUT OF SERVICESubstantial Completion1 dayThu 1/21/21Thu 1/21/21
541Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICE9 daysMon 1/18/21Thu 1/28/21
542Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICEDrywall Abatement5 daysMon 1/18/21Fri 1/22/21
543Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICEDemolish old piping-Riser Outage5 daysTue 1/19/21Mon 1/25/21
544Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICEInstall New Piping5 daysTue 1/19/21Mon 1/25/21
545Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICETest/Insulate5 daysWed 1/20/21Tue 1/26/21
546Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICERestore Service1 dayTue 1/26/21Tue 1/26/21
547Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICEDrywall Repair/Paint6 daysWed 1/20/21Wed 1/27/21
548Riser #6-2 Replacement, J Hall Closet 17th-3rd (L Hall Closet)-OUT OF SERVICESubstantial Completion1 dayThu 1/28/21Thu 1/28/21
549Riser #2-1 Replacement, E Living Room 41st-3rd17 daysMon 1/25/21Tue 2/16/21
550Riser #2-1 Replacement, E Living Room 41st-3rdDrywall Abatement13 daysMon 1/25/21Wed 2/10/21
551Riser #2-1 Replacement, E Living Room 41st-3rdDemolish old piping-Riser Outage13 daysTue 1/26/21Thu 2/11/21
552Riser #2-1 Replacement, E Living Room 41st-3rdInstall New Piping13 daysTue 1/26/21Thu 2/11/21
553Riser #2-1 Replacement, E Living Room 41st-3rdTest/Insulate13 daysWed 1/27/21Fri 2/12/21
554Riser #2-1 Replacement, E Living Room 41st-3rdRestore Service1 dayFri 2/12/21Fri 2/12/21
555Riser #2-1 Replacement, E Living Room 41st-3rdDrywall Repair/Paint14 daysWed 1/27/21Mon 2/15/21
556Riser #2-1 Replacement, E Living Room 41st-3rdSubstantial Completion1 dayTue 2/16/21Tue 2/16/21
557Riser #2-3 Replacement, G Living Room 41st-3rd17 daysThu 2/11/21Fri 3/5/21
558Riser #2-3 Replacement, G Living Room 41st-3rdDrywall Abatement13 daysThu 2/11/21Mon 3/1/21
559Riser #2-3 Replacement, G Living Room 41st-3rdDemolish old piping-Riser Outage13 daysFri 2/12/21Tue 3/2/21
560Riser #2-3 Replacement, G Living Room 41st-3rdInstall New Piping13 daysFri 2/12/21Tue 3/2/21
561Riser #2-3 Replacement, G Living Room 41st-3rdTest/Insulate13 daysMon 2/15/21Wed 3/3/21
562Riser #2-3 Replacement, G Living Room 41st-3rdRestore Service1 dayWed 3/3/21Wed 3/3/21
563Riser #2-3 Replacement, G Living Room 41st-3rdDrywall Repair/Paint14 daysMon 2/15/21Thu 3/4/21
564Riser #2-3 Replacement, G Living Room 41st-3rdSubstantial Completion1 dayFri 3/5/21Fri 3/5/21
565Riser #2-4 Replacement, H Living 41st-3rd17 daysTue 3/2/21Wed 3/24/21
566Riser #2-4 Replacement, H Living 41st-3rdDrywall Abatement13 daysTue 3/2/21Thu 3/18/21
567Riser #2-4 Replacement, H Living 41st-3rdDemolish old piping-Riser Outage13 daysWed 3/3/21Fri 3/19/21
568Riser #2-4 Replacement, H Living 41st-3rdInstall New Piping13 daysWed 3/3/21Fri 3/19/21
569Riser #2-4 Replacement, H Living 41st-3rdTest/Insulate13 daysThu 3/4/21Mon 3/22/21
570Riser #2-4 Replacement, H Living 41st-3rdRestore Service1 dayMon 3/22/21Mon 3/22/21
571Riser #2-4 Replacement, H Living 41st-3rdDrywall Repair/Paint14 daysThu 3/4/21Tue 3/23/21
572Riser #2-4 Replacement, H Living 41st-3rdSubstantial Completion1 dayWed 3/24/21Wed 3/24/21
573Riser #4-4 Replacement, A/B Bathrooms 17th-3rd9 daysFri 3/19/21Wed 3/31/21
574Riser #4-4 Replacement, A/B Bathrooms 17th-3rdDrywall Abatement5 daysFri 3/19/21Thu 3/25/21
575Riser #4-4 Replacement, A/B Bathrooms 17th-3rdDemolish old piping-Riser Outage5 daysMon 3/22/21Fri 3/26/21
576Riser #4-4 Replacement, A/B Bathrooms 17th-3rdInstall New Piping5 daysMon 3/22/21Fri 3/26/21
577Riser #4-4 Replacement, A/B Bathrooms 17th-3rdTest/Insulate5 daysTue 3/23/21Mon 3/29/21
578Riser #4-4 Replacement, A/B Bathrooms 17th-3rdRestore Service1 dayMon 3/29/21Mon 3/29/21
579Riser #4-4 Replacement, A/B Bathrooms 17th-3rdDrywall Repair/Paint6 daysTue 3/23/21Tue 3/30/21
580Riser #4-4 Replacement, A/B Bathrooms 17th-3rdSubstantial Completion1 dayWed 3/31/21Wed 3/31/21
581Riser #2-6 Replacement, J Living Room 41st-3rd17 daysFri 3/26/21Mon 4/19/21
582Riser #2-6 Replacement, J Living Room 41st-3rdDrywall Abatement13 daysFri 3/26/21Tue 4/13/21
583Riser #2-6 Replacement, J Living Room 41st-3rdDemolish old piping-Riser Outage13 daysMon 3/29/21Wed 4/14/21
584Riser #2-6 Replacement, J Living Room 41st-3rdInstall New Piping13 daysMon 3/29/21Wed 4/14/21
585Riser #2-6 Replacement, J Living Room 41st-3rdTest/Insulate13 daysTue 3/30/21Thu 4/15/21
586Riser #2-6 Replacement, J Living Room 41st-3rdRestore Service1 dayThu 4/15/21Thu 4/15/21
587Riser #2-6 Replacement, J Living Room 41st-3rdDrywall Repair/Paint14 daysTue 3/30/21Fri 4/16/21
588Riser #2-6 Replacement, J Living Room 41st-3rdSubstantial Completion1 dayMon 4/19/21Mon 4/19/21
589Riser #4-3 Replacement, A Living Room 17th-3rd9 daysWed 4/14/21Mon 4/26/21
590Riser #4-3 Replacement, A Living Room 17th-3rdDrywall Abatement4 daysWed 4/14/21Mon 4/19/21
591Riser #4-3 Replacement, A Living Room 17th-3rdDemolish old piping-Riser Outage4 daysThu 4/15/21Tue 4/20/21
592Riser #4-3 Replacement, A Living Room 17th-3rdInstall New Piping4 daysThu 4/15/21Tue 4/20/21
593Riser #4-3 Replacement, A Living Room 17th-3rdTest/Insulate5 daysFri 4/16/21Thu 4/22/21
594Riser #4-3 Replacement, A Living Room 17th-3rdRestore Service1 dayWed 4/21/21Wed 4/21/21
595Riser #4-3 Replacement, A Living Room 17th-3rdDrywall Repair/Paint6 daysFri 4/16/21Fri 4/23/21
596Riser #4-3 Replacement, A Living Room 17th-3rdSubstantial Completion1 dayMon 4/26/21Mon 4/26/21
597Riser #4-1 Replacement, C Living Room 17th-3rd9 daysTue 4/20/21Fri 4/30/21
598Riser #4-1 Replacement, C Living Room 17th-3rdDrywall Abatement4 daysTue 4/20/21Fri 4/23/21
599Riser #4-1 Replacement, C Living Room 17th-3rdDemolish old piping-Riser Outage4 daysWed 4/21/21Mon 4/26/21
600Riser #4-1 Replacement, C Living Room 17th-3rdInstall New Piping4 daysWed 4/21/21Mon 4/26/21
601Riser #4-1 Replacement, C Living Room 17th-3rdTest/Insulate5 daysThu 4/22/21Wed 4/28/21
602Riser #4-1 Replacement, C Living Room 17th-3rdRestore Service1 dayTue 4/27/21Tue 4/27/21
603Riser #4-1 Replacement, C Living Room 17th-3rdDrywall Repair/Paint6 daysThu 4/22/21Thu 4/29/21
604Riser #4-1 Replacement, C Living Room 17th-3rdSubstantial Completion1 dayFri 4/30/21Fri 4/30/21
605Riser #3-1 Replacement, C Living Room 41st-18th12 daysMon 4/26/21Tue 5/11/21
606Riser #3-1 Replacement, C Living Room 41st-18thDrywall Abatement8 daysMon 4/26/21Wed 5/5/21
607Riser #3-1 Replacement, C Living Room 41st-18thDemolish old piping-Riser Outage8 daysTue 4/27/21Thu 5/6/21
608Riser #3-1 Replacement, C Living Room 41st-18thInstall New Piping8 daysTue 4/27/21Thu 5/6/21
609Riser #3-1 Replacement, C Living Room 41st-18thTest/Insulate8 daysWed 4/28/21Fri 5/7/21
610Riser #3-1 Replacement, C Living Room 41st-18thRestore Service1 dayFri 5/7/21Fri 5/7/21
611Riser #3-1 Replacement, C Living Room 41st-18thDrywall Repair/Paint9 daysWed 4/28/21Mon 5/10/21
612Riser #3-1 Replacement, C Living Room 41st-18thSubstantial Completion1 dayTue 5/11/21Tue 5/11/21
613Riser #3-2 Replacement, B Living Room 41st-18th12 daysThu 5/6/21Fri 5/21/21
614Riser #3-2 Replacement, B Living Room 41st-18thDrywall Abatement8 daysThu 5/6/21Mon 5/17/21
615Riser #3-2 Replacement, B Living Room 41st-18thDemolish old piping-Riser Outage8 daysFri 5/7/21Tue 5/18/21
616Riser #3-2 Replacement, B Living Room 41st-18thInstall New Piping8 daysFri 5/7/21Tue 5/18/21
617Riser #3-2 Replacement, B Living Room 41st-18thTest/Insulate8 daysMon 5/10/21Wed 5/19/21
618Riser #3-2 Replacement, B Living Room 41st-18thRestore Service1 dayWed 5/19/21Wed 5/19/21
619Riser #3-2 Replacement, B Living Room 41st-18thDrywall Repair/Paint9 daysMon 5/10/21Thu 5/20/21
620Riser #3-2 Replacement, B Living Room 41st-18thSubstantial Completion1 dayFri 5/21/21Fri 5/21/21
621Riser Valve Installation [SHOULDER #2]10 daysThu 5/13/21Wed 5/26/21
622Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]17 daysWed 5/26/21Fri 6/18/21
623Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Drywall Abatement13 daysWed 5/26/21Mon 6/14/21
624Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Demolish old piping-Riser Outage13 daysThu 5/27/21Tue 6/15/21
625Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Install New Piping13 daysThu 5/27/21Tue 6/15/21
626Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Test/Insulate13 daysFri 5/28/21Wed 6/16/21
627Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Restore Service1 dayWed 6/16/21Wed 6/16/21
628Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Drywall Repair/Paint14 daysFri 5/28/21Thu 6/17/21
629Riser #2-5 Replacement, I Living & H/I Bathrooms 41st-3rd [SHOULDER]Substantial Completion1 dayFri 6/18/21Fri 6/18/21
630Riser #4-2 Replacement, B Living Room 17th-3rd9 daysTue 6/15/21Fri 6/25/21
631Riser #4-2 Replacement, B Living Room 17th-3rdDrywall Abatement4 daysTue 6/15/21Fri 6/18/21
632Riser #4-2 Replacement, B Living Room 17th-3rdDemolish old piping-Riser Outage4 daysWed 6/16/21Mon 6/21/21
633Riser #4-2 Replacement, B Living Room 17th-3rdInstall New Piping4 daysWed 6/16/21Mon 6/21/21
634Riser #4-2 Replacement, B Living Room 17th-3rdTest/Insulate5 daysThu 6/17/21Wed 6/23/21
635Riser #4-2 Replacement, B Living Room 17th-3rdRestore Service1 dayTue 6/22/21Tue 6/22/21
636Riser #4-2 Replacement, B Living Room 17th-3rdDrywall Repair/Paint6 daysThu 6/17/21Thu 6/24/21
637Riser #4-2 Replacement, B Living Room 17th-3rdSubstantial Completion1 dayFri 6/25/21Fri 6/25/21
638Riser #3-3 Replacement, A Living Room 41st-18th12 daysMon 6/21/21Wed 7/7/21
639Riser #3-3 Replacement, A Living Room 41st-18thDrywall Abatement8 daysMon 6/21/21Wed 6/30/21
640Riser #3-3 Replacement, A Living Room 41st-18thDemolish old piping-Riser Outage8 daysTue 6/22/21Thu 7/1/21
641Riser #3-3 Replacement, A Living Room 41st-18thInstall New Piping8 daysTue 6/22/21Thu 7/1/21
642Riser #3-3 Replacement, A Living Room 41st-18thTest/Insulate8 daysWed 6/23/21Fri 7/2/21
643Riser #3-3 Replacement, A Living Room 41st-18thRestore Service1 dayFri 7/2/21Fri 7/2/21
644Riser #3-3 Replacement, A Living Room 41st-18thDrywall Repair/Paint9 daysWed 6/23/21Tue 7/6/21
645Riser #3-3 Replacement, A Living Room 41st-18thSubstantial Completion1 dayWed 7/7/21Wed 7/7/21
646Riser #3-4 Replacement, A/B Bathrooms 41st-18th12 daysThu 7/1/21Mon 7/19/21
647Riser #3-4 Replacement, A/B Bathrooms 41st-18thDrywall Abatement8 daysThu 7/1/21Tue 7/13/21
648Riser #3-4 Replacement, A/B Bathrooms 41st-18thDemolish old piping-Riser Outage8 daysFri 7/2/21Wed 7/14/21
649Riser #3-4 Replacement, A/B Bathrooms 41st-18thInstall New Piping8 daysFri 7/2/21Wed 7/14/21
650Riser #3-4 Replacement, A/B Bathrooms 41st-18thTest/Insulate8 daysTue 7/6/21Thu 7/15/21
651Riser #3-4 Replacement, A/B Bathrooms 41st-18thRestore Service1 dayThu 7/15/21Thu 7/15/21
652Riser #3-4 Replacement, A/B Bathrooms 41st-18thDrywall Repair/Paint9 daysTue 7/6/21Fri 7/16/21
653Riser #3-4 Replacement, A/B Bathrooms 41st-18thSubstantial Completion1 dayMon 7/19/21Mon 7/19/21
654Riser #3-5 Replacement, N/M Bathrooms 41st-18th12 daysWed 7/14/21Thu 7/29/21
655Riser #3-5 Replacement, N/M Bathrooms 41st-18thDrywall Abatement8 daysWed 7/14/21Fri 7/23/21
656Riser #3-5 Replacement, N/M Bathrooms 41st-18thDemolish old piping-Riser Outage8 daysThu 7/15/21Mon 7/26/21
657Riser #3-5 Replacement, N/M Bathrooms 41st-18thInstall New Piping8 daysThu 7/15/21Mon 7/26/21
658Riser #3-5 Replacement, N/M Bathrooms 41st-18thTest/Insulate8 daysFri 7/16/21Tue 7/27/21
659Riser #3-5 Replacement, N/M Bathrooms 41st-18thRestore Service1 dayTue 7/27/21Tue 7/27/21
660Riser #3-5 Replacement, N/M Bathrooms 41st-18thDrywall Repair/Paint9 daysFri 7/16/21Wed 7/28/21
661Riser #3-5 Replacement, N/M Bathrooms 41st-18thSubstantial Completion1 dayThu 7/29/21Thu 7/29/21
662Riser #4-5 Replacement, N/M Bathrooms 17th-3rd9 daysMon 7/26/21Thu 8/5/21
663Riser #4-5 Replacement, N/M Bathrooms 17th-3rdDrywall Abatement4 daysMon 7/26/21Thu 7/29/21
664Riser #4-5 Replacement, N/M Bathrooms 17th-3rdDemolish old piping-Riser Outage4 daysTue 7/27/21Fri 7/30/21
665Riser #4-5 Replacement, N/M Bathrooms 17th-3rdInstall New Piping4 daysTue 7/27/21Fri 7/30/21
666Riser #4-5 Replacement, N/M Bathrooms 17th-3rdTest/Insulate5 daysWed 7/28/21Tue 8/3/21
667Riser #4-5 Replacement, N/M Bathrooms 17th-3rdRestore Service1 dayMon 8/2/21Mon 8/2/21
668Riser #4-5 Replacement, N/M Bathrooms 17th-3rdDrywall Repair/Paint6 daysWed 7/28/21Wed 8/4/21
669Riser #4-5 Replacement, N/M Bathrooms 17th-3rdSubstantial Completion1 dayThu 8/5/21Thu 8/5/21
670Riser #3-6 Replacement, M Living Room 41st-18th12 daysFri 7/30/21Mon 8/16/21
671Riser #3-6 Replacement, M Living Room 41st-18thDrywall Abatement8 daysFri 7/30/21Tue 8/10/21
672Riser #3-6 Replacement, M Living Room 41st-18thDemolish old piping-Riser Outage8 daysMon 8/2/21Wed 8/11/21
673Riser #3-6 Replacement, M Living Room 41st-18thInstall New Piping8 daysMon 8/2/21Wed 8/11/21
674Riser #3-6 Replacement, M Living Room 41st-18thTest/Insulate8 daysTue 8/3/21Thu 8/12/21
675Riser #3-6 Replacement, M Living Room 41st-18thRestore Service1 dayThu 8/12/21Thu 8/12/21
676Riser #3-6 Replacement, M Living Room 41st-18thDrywall Repair/Paint9 daysTue 8/3/21Fri 8/13/21
677Riser #3-6 Replacement, M Living Room 41st-18thSubstantial Completion1 dayMon 8/16/21Mon 8/16/21
678Riser #4-7 Replacement, M Living Room 17th-3rd9 daysWed 8/11/21Mon 8/23/21
679Riser #4-7 Replacement, M Living Room 17th-3rdDrywall Abatement4 daysWed 8/11/21Mon 8/16/21
680Riser #4-7 Replacement, M Living Room 17th-3rdDemolish old piping-Riser Outage4 daysThu 8/12/21Tue 8/17/21
681Riser #4-7 Replacement, M Living Room 17th-3rdInstall New Piping4 daysThu 8/12/21Tue 8/17/21
682Riser #4-7 Replacement, M Living Room 17th-3rdTest/Insulate5 daysFri 8/13/21Thu 8/19/21
683Riser #4-7 Replacement, M Living Room 17th-3rdRestore Service1 dayWed 8/18/21Wed 8/18/21
684Riser #4-7 Replacement, M Living Room 17th-3rdDrywall Repair/Paint6 daysFri 8/13/21Fri 8/20/21
685Riser #4-7 Replacement, M Living Room 17th-3rdSubstantial Completion1 dayMon 8/23/21Mon 8/23/21
686Riser #3-7 Replacement, L Living Room 41st-18th12 daysTue 8/17/21Wed 9/1/21
687Riser #3-7 Replacement, L Living Room 41st-18thDrywall Abatement8 daysTue 8/17/21Thu 8/26/21
688Riser #3-7 Replacement, L Living Room 41st-18thDemolish old piping-Riser Outage8 daysWed 8/18/21Fri 8/27/21
689Riser #3-7 Replacement, L Living Room 41st-18thInstall New Piping8 daysWed 8/18/21Fri 8/27/21
690Riser #3-7 Replacement, L Living Room 41st-18thTest/Insulate8 daysThu 8/19/21Mon 8/30/21
691Riser #3-7 Replacement, L Living Room 41st-18thRestore Service1 dayMon 8/30/21Mon 8/30/21
692Riser #3-7 Replacement, L Living Room 41st-18thDrywall Repair/Paint9 daysThu 8/19/21Tue 8/31/21
693Riser #3-7 Replacement, L Living Room 41st-18thSubstantial Completion1 dayWed 9/1/21Wed 9/1/21
694Riser #4-8 Replacement, L Living Room 17th-3rd9 daysFri 8/27/21Thu 9/9/21
695Riser #4-8 Replacement, L Living Room 17th-3rdDrywall Abatement4 daysFri 8/27/21Wed 9/1/21
696Riser #4-8 Replacement, L Living Room 17th-3rdDemolish old piping-Riser Outage4 daysMon 8/30/21Thu 9/2/21
697Riser #4-8 Replacement, L Living Room 17th-3rdInstall New Piping4 daysMon 8/30/21Thu 9/2/21
698Riser #4-8 Replacement, L Living Room 17th-3rdTest/Insulate5 daysTue 8/31/21Tue 9/7/21
699Riser #4-8 Replacement, L Living Room 17th-3rdRestore Service1 dayFri 9/3/21Fri 9/3/21
700Riser #4-8 Replacement, L Living Room 17th-3rdDrywall Repair/Paint6 daysTue 8/31/21Wed 9/8/21
701Riser #4-8 Replacement, L Living Room 17th-3rdSubstantial Completion1 dayThu 9/9/21Thu 9/9/21
702Riser #5-3 Replacement, K Living Room 41st-18th12 daysThu 9/2/21Mon 9/20/21
703Riser #5-3 Replacement, K Living Room 41st-18thDrywall Abatement8 daysThu 9/2/21Tue 9/14/21
704Riser #5-3 Replacement, K Living Room 41st-18thDemolish old piping-Riser Outage8 daysFri 9/3/21Wed 9/15/21
705Riser #5-3 Replacement, K Living Room 41st-18thInstall New Piping8 daysFri 9/3/21Wed 9/15/21
706Riser #5-3 Replacement, K Living Room 41st-18thTest/Insulate8 daysTue 9/7/21Thu 9/16/21
707Riser #5-3 Replacement, K Living Room 41st-18thRestore Service1 dayThu 9/16/21Thu 9/16/21
708Riser #5-3 Replacement, K Living Room 41st-18thDrywall Repair/Paint9 daysTue 9/7/21Fri 9/17/21
709Riser #5-3 Replacement, K Living Room 41st-18thSubstantial Completion1 dayMon 9/20/21Mon 9/20/21
710Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]10 daysWed 9/15/21Tue 9/28/21
711Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Drywall Abatement5 daysWed 9/15/21Tue 9/21/21
712Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Demolish old piping-Riser Outage5 daysFri 9/17/21Thu 9/23/21
713Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Install New Piping5 daysFri 9/17/21Thu 9/23/21
714Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Test/Insulate5 daysMon 9/20/21Fri 9/24/21
715Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Restore Service1 dayFri 9/24/21Fri 9/24/21
716Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Drywall Repair/Paint6 daysMon 9/20/21Mon 9/27/21
717Express Riser Zone #6 Replacement, K Kitchen & Bathroom [SHOULDER #3]Substantial Completion1 dayTue 9/28/21Tue 9/28/21
718Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]9 daysWed 9/22/21Mon 10/4/21
719Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Drywall Abatement5 daysWed 9/22/21Tue 9/28/21
720Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Demolish old piping-Riser Outage5 daysThu 9/23/21Wed 9/29/21
721Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Install New Piping5 daysThu 9/23/21Wed 9/29/21
722Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Test/Insulate5 daysFri 9/24/21Thu 9/30/21
723Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Restore Service1 dayThu 9/30/21Thu 9/30/21
724Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Drywall Repair/Paint6 daysFri 9/24/21Fri 10/1/21
725Express Riser Zone #4 Replacement, Elevator Lobby [SHOULDER #3]Substantial Completion1 dayMon 10/4/21Mon 10/4/21
726Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]17 daysWed 9/29/21Thu 10/21/21
727Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Drywall Abatement13 daysWed 9/29/21Fri 10/15/21
728Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Demolish old piping-Riser Outage13 daysThu 9/30/21Mon 10/18/21
729Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Install New Piping13 daysThu 9/30/21Mon 10/18/21
730Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Test/Insulate13 daysFri 10/1/21Tue 10/19/21
731Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Restore Service1 dayTue 10/19/21Tue 10/19/21
732Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Drywall Repair/Paint14 daysFri 10/1/21Wed 10/20/21
733Riser #2-2 Replacement, F Living & F/G Bathrooms 41st-3rd [SHOULDER]Substantial Completion1 dayThu 10/21/21Thu 10/21/21
734Riser #6-3 Replacement, K Living Room 17th-3rd9 daysMon 10/18/21Thu 10/28/21
735Riser #6-3 Replacement, K Living Room 17th-3rdDrywall Abatement5 daysMon 10/18/21Fri 10/22/21
736Riser #6-3 Replacement, K Living Room 17th-3rdDemolish old piping-Riser Outage5 daysTue 10/19/21Mon 10/25/21
737Riser #6-3 Replacement, K Living Room 17th-3rdInstall New Piping5 daysTue 10/19/21Mon 10/25/21
738Riser #6-3 Replacement, K Living Room 17th-3rdTest/Insulate5 daysWed 10/20/21Tue 10/26/21
739Riser #6-3 Replacement, K Living Room 17th-3rdRestore Service1 dayTue 10/26/21Tue 10/26/21
740Riser #6-3 Replacement, K Living Room 17th-3rdDrywall Repair/Paint6 daysWed 10/20/21Wed 10/27/21
741Riser #6-3 Replacement, K Living Room 17th-3rdSubstantial Completion1 dayThu 10/28/21Thu 10/28/21
742Riser #1-4 Replacement, D Bedroom 41st-3rd17 daysMon 10/25/21Tue 11/16/21
743Riser #1-4 Replacement, D Bedroom 41st-3rdDrywall Abatement13 daysMon 10/25/21Wed 11/10/21
744Riser #1-4 Replacement, D Bedroom 41st-3rdDemolish old piping-Riser Outage13 daysTue 10/26/21Thu 11/11/21
745Riser #1-4 Replacement, D Bedroom 41st-3rdInstall New Piping13 daysTue 10/26/21Thu 11/11/21
746Riser #1-4 Replacement, D Bedroom 41st-3rdTest/Insulate13 daysWed 10/27/21Fri 11/12/21
747Riser #1-4 Replacement, D Bedroom 41st-3rdRestore Service1 dayFri 11/12/21Fri 11/12/21
748Riser #1-4 Replacement, D Bedroom 41st-3rdDrywall Repair/Paint14 daysWed 10/27/21Mon 11/15/21
749Riser #1-4 Replacement, D Bedroom 41st-3rdSubstantial Completion1 dayTue 11/16/21Tue 11/16/21
750Riser #4-6 Replacement, N Living Room 17th-3rd9 daysThu 11/11/21Tue 11/23/21
751Riser #4-6 Replacement, N Living Room 17th-3rdDrywall Abatement5 daysThu 11/11/21Wed 11/17/21
752Riser #4-6 Replacement, N Living Room 17th-3rdDemolish old piping-Riser Outage5 daysFri 11/12/21Thu 11/18/21
753Riser #4-6 Replacement, N Living Room 17th-3rdInstall New Piping5 daysFri 11/12/21Thu 11/18/21
754Riser #4-6 Replacement, N Living Room 17th-3rdTest/Insulate5 daysMon 11/15/21Fri 11/19/21
755Riser #4-6 Replacement, N Living Room 17th-3rdRestore Service1 dayFri 11/19/21Fri 11/19/21
756Riser #4-6 Replacement, N Living Room 17th-3rdDrywall Repair/Paint6 daysMon 11/15/21Mon 11/22/21
757Riser #4-6 Replacement, N Living Room 17th-3rdSubstantial Completion1 dayTue 11/23/21Tue 11/23/21
758Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]17 daysThu 11/18/21Tue 12/14/21
759Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Drywall Abatement13 daysThu 11/18/21Wed 12/8/21
760Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Demolish old piping-Riser Outage13 daysFri 11/19/21Thu 12/9/21
761Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Install New Piping13 daysFri 11/19/21Thu 12/9/21
762Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Test/Insulate13 daysMon 11/22/21Fri 12/10/21
763Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Restore Service1 dayFri 12/10/21Fri 12/10/21
764Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Drywall Repair/Paint14 daysMon 11/22/21Mon 12/13/21
765Riser #1-1 Replacement, E Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Substantial Completion1 dayTue 12/14/21Tue 12/14/21
766Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]17 daysThu 12/9/21Tue 1/4/22
767Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Drywall Abatement13 daysThu 12/9/21Wed 12/29/21
768Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Demolish old piping-Riser Outage13 daysFri 12/10/21Thu 12/30/21
769Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Install New Piping13 daysFri 12/10/21Thu 12/30/21
770Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Test/Insulate13 daysMon 12/13/21Fri 12/31/21
771Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Restore Service1 dayFri 12/31/21Fri 12/31/21
772Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Drywall Repair/Paint14 daysMon 12/13/21Mon 1/3/22
773Riser #1-5 Replacement, C Bathrooms 41st-3rd [NO ADD'L ABATEMENT]Substantial Completion1 dayTue 1/4/22Tue 1/4/22
774Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]13 daysThu 12/30/21Mon 1/17/22
775Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Drywall Abatement7 daysThu 12/30/21Fri 1/7/22
776Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Demolish old piping-Riser Outage7 daysFri 12/31/21Mon 1/10/22
777Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Install New Piping7 daysFri 12/31/21Mon 1/10/22
778Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Test/Insulate7 daysMon 1/3/22Tue 1/11/22
779Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Restore Service1 dayTue 1/11/22Tue 1/11/22
780Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Drywall Repair/Paint10 daysMon 1/3/22Fri 1/14/22
781Riser #5-1 Replacement, J Bathrooms 41st-18th [NO ADD'L ABATEMENT]Substantial Completion1 dayMon 1/17/22Mon 1/17/22
782Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]10 daysMon 1/10/22Fri 1/21/22
783Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Drywall Abatement4 daysMon 1/10/22Thu 1/13/22
784Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Demolish old piping-Riser Outage4 daysTue 1/11/22Fri 1/14/22
785Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Install New Piping4 daysTue 1/11/22Fri 1/14/22
786Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Test/Insulate4 daysWed 1/12/22Mon 1/17/22
787Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Restore Service1 dayMon 1/17/22Mon 1/17/22
788Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Drywall Repair/Paint7 daysWed 1/12/22Thu 1/20/22
789Riser #6-1 Replacement, J Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Substantial Completion1 dayFri 1/21/22Fri 1/21/22
790Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]13 daysFri 1/14/22Tue 2/1/22
791Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Drywall Abatement7 daysFri 1/14/22Mon 1/24/22
792Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Demolish old piping-Riser Outage7 daysMon 1/17/22Tue 1/25/22
793Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Install New Piping7 daysMon 1/17/22Tue 1/25/22
794Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Test/Insulate7 daysTue 1/18/22Wed 1/26/22
795Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Restore Service1 dayWed 1/26/22Wed 1/26/22
796Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Drywall Repair/Paint10 daysTue 1/18/22Mon 1/31/22
797Riser #5-4 Replacement, L Bathrooms 41st-18th [NO ADD'L ABATEMENT]Substantial Completion1 dayTue 2/1/22Tue 2/1/22
798Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]10 daysTue 1/25/22Mon 2/7/22
799Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Drywall Abatement4 daysTue 1/25/22Fri 1/28/22
800Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Demolish old piping-Riser Outage4 daysWed 1/26/22Mon 1/31/22
801Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Install New Piping4 daysWed 1/26/22Mon 1/31/22
802Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Test/Insulate4 daysThu 1/27/22Tue 2/1/22
803Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Restore Service1 dayTue 2/1/22Tue 2/1/22
804Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Drywall Repair/Paint7 daysThu 1/27/22Fri 2/4/22
805Riser #6-4 Replacement, L Bathrooms 17th-3rd [NO ADD'L ABATEMENT]Substantial Completion1 dayMon 2/7/22Mon 2/7/22